How can you prevent bridging in a dilute phase pneumatic conveying system?



How can you prevent bridging in a dilute phase pneumatic conveying system?..

Answer / Dilbagh Singh

Bridging can be prevented by:
1. Proper selection of materials with good flow properties.
2. Maintaining adequate velocity and turbulence to keep particles in suspension.
3. Minimizing pipe bends and ensuring proper radius and spacing.
4. Adding vibration or air agitation to the conveying line.
5. Adjusting the material feed rate or slurry composition.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Chemical Engineering Interview Questions

How can hexavalent chromium be removed from aqueous waste streams?

1 Answers  


Chemical Engineering Unit Operation - Which of the sequence below represent a feasible flows of ethanol processing plants using cellulose as starting material? A. raw material --> heat exchanger --> distillation column --> reactor. B. reactor --> distillation column --> raw material --> heat exchanger. C. heat exchanger --> raw material --> distillation column --> reactor. D. raw material --> heat exchanger --> reactor --> distillation column. E. distillation column --> raw material --> reactor --> heat exchanger.

1 Answers  


what is vacuum....?

6 Answers   UPL,


What is gibbs free energy?

1 Answers  


Is there any facility to complete M.TECH CHEMICal eNGINEERING IN INDIA. Any college providing the same.

4 Answers  


What are some characteristics of bulk solids that can affect their ability to flow properly?

1 Answers  


HOw to derive reynolds equation?

1 Answers  


What are the applications of screen analysis in the chemical industry?

1 Answers  


why PH scale range is 14? why it is not less or not greater than 14? solution of HCl or hydrogen containing liquid has a PH. but if the solution is KMnO4 here not hydrogen power does it PH? explain plz....

1 Answers  


What does the catalystic converter on an automobile do?

3 Answers  


We are having proplem with the persperation smell in ETT/ECHO room in our cardiac hospital.The 2 Ton of AC is not conditioning the environment. We have to use exhaust fan to through out of the room bad air. Could anyone suggest how to coup with this effectively using chemical engineering. Any permanent solution to neutralise the bad smell.The Air freshners are not doing enough instead making a bad odour.

1 Answers  


ENGINEERING MECHANIC - EXAMPLE 15.2 : A cantilever beam of length L = 3 m carries a uniformly distributed load (UDL) of W = 20 N / m throughout the length. Calculate the bending moment, BM of the beam near the fixed end. What is the shear force, SF at this point? Let SF = -WL, BM = -LWL/2.

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)