a) Wall plastering in CM 1:4 of 12 mm thick for 100 m2:-
Volume = 100 x (12/1000) = 1.20 m3
Add 30 to 35% as bulking of sand = 0.36 m3
Add 20 as wastage of sand = 0.312 m3
Total = 1.872 m3
= (1.872/1+4) = 0.374 m3
Cement = 0.374 x 30 = 10.77 bags
Sand = 0.374 x 4 = 1.496 m3
b) For 100 m3 of solid Block masonry in CM 1:6 mix 8” thick:-
Volume = 100 x 0.2 (Thickness of wall)
= 20 m3
No. of blocks required = 20/(0.4 x 0.2 x 0.2)
= 12502 No’s
Volume of mortar = 20-{0.39 x 0.19 x 0.19 x 1250}
= 20 – 17.598 = 2.40 m3
Note: 200mm – 10 mm for mortar thickness = 190 mm
Blocks =17.598/(0.4 x 0.2 x 0.2) =1100 No’s
Add 2% wastage = 22
Total = 1122 No’s
Increase by 25% for dry mortar = 3 M3
= 3/ (1+6) = 0.429 M3
Cement = 0.429 x 30 = 12.50 bags
Sand = 0.429 x 6 = 2.57 M3
Blocks =1122 No’s
Is This Answer Correct ? | 1 Yes | 0 No |
Dear Sir,
In b) part 100 m3 ur 100 m2. if 100 m3 as mentioned then why we multiply with 0.2 block thickness.
Is This Answer Correct ? | 0 Yes | 0 No |
If we buy crush sand for 3200/ Brass and cement for Rs350 /Bag and flyash 1200 / tonne....and my production is 230 Bricks per bag than how much cost is required for 1 flyash brick?
shuttering consumption per square feet in multi storeyed building?
how to tie 10 legged stirrups
how to calculate the steel for 450 sft slab, please tell me the solution method
What things architect have to take care of before starting any project?
What is the meaning and full form of FTA and MTA in plumbing material
What is the formulae of percentage of steel
what is the pile
1 Answers Chandra Group, GVR Constructions, Simplex,
For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?
what is the process of repair the structure in whitch reinforcement is open
What are the different types of foundation?
what is the use of bottom reinforcement in Cantilever Beam?