Answer Posted / mohammed tausif
a) Wall plastering in CM 1:4 of 12 mm thick for 100 m2:-
Volume = 100 x (12/1000) = 1.20 m3
Add 30 to 35% as bulking of sand = 0.36 m3
Add 20 as wastage of sand = 0.312 m3
Total = 1.872 m3
= (1.872/1+4) = 0.374 m3
Cement = 0.374 x 30 = 10.77 bags
Sand = 0.374 x 4 = 1.496 m3
b) For 100 m3 of solid Block masonry in CM 1:6 mix 8” thick:-
Volume = 100 x 0.2 (Thickness of wall)
= 20 m3
No. of blocks required = 20/(0.4 x 0.2 x 0.2)
= 12502 No’s
Volume of mortar = 20-{0.39 x 0.19 x 0.19 x 1250}
= 20 – 17.598 = 2.40 m3
Note: 200mm – 10 mm for mortar thickness = 190 mm
Blocks =17.598/(0.4 x 0.2 x 0.2) =1100 No’s
Add 2% wastage = 22
Total = 1122 No’s
Increase by 25% for dry mortar = 3 M3
= 3/ (1+6) = 0.429 M3
Cement = 0.429 x 30 = 12.50 bags
Sand = 0.429 x 6 = 2.57 M3
Blocks =1122 No’s
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
What are the responsibilities of a construction manager?
five requirements of infill panels for walls?
in block masonry l=10',b=0.5',H=10',Calculate cement ,sand and no.Of blocks?
Rate analysis of Vitrified tile in cement mortor 1:3
How much of fly ash is allowable in Portland cement and what is the disadvantage when the level of fly ash is increased?
explain the rale of the government in the construction industry
What happens when,in Prestressed girder the HDPE duct and cone size is provided more than required? (technical answer expected)
The building has 12 columns of 12x9 in 3 rows of 4 each in a plot of 50'x30', The central row is strengthened with 16mm twisted rods. The roof area is 1500 sft including balconies. calculate the load factor per sft. Also indicate the number of roofs the building can withstand.
what is the difference between replacement of cement by groundnut shell ash
can stub column take the load as main column
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.
is basic cost of the material includes tax?
How do you change a dimension value in solidsworks?
What is rate of concrete surface rendering work per sqm
What are the different approaches in designing the floors of the service reservoirs?