How to calculate cement quantity in m20 concrete

Answers were Sorted based on User's Feedback



How to calculate cement quantity in m20 concrete..

Answer / jayaprakashsst

M20 concrete means 1:1.5:3

M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg = 8.22 bags

Is This Answer Correct ?    14 Yes 1 No

How to calculate cement quantity in m20 concrete..

Answer / jayaprakashsst

calculation of cement quantity in m20 concrete

M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg = 8.22 kgs

Is This Answer Correct ?    4 Yes 2 No

Post New Answer

More Civil Engineering Interview Questions

whats the field test of cement,aggregate and water

6 Answers  


Difference between pre-tensioning and post-tensioning.

0 Answers  


wat is meant by aerocon bricks?

6 Answers   L&T, Real Estate,


what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.

0 Answers   Gayatri,


Power grids in two adjacent states(A&B) are interconnected. Can power grid in state A can be represented by Thevenin Equivalent Circuit. If not explain Why?

0 Answers  






wat is the optimum mix design for M25 grade of concrete ? is the ratio 1:1.5:3.65 correct?

7 Answers   ACC,


what is the effect of duration of earth quake on framed structures ?

0 Answers  


what is the rate for per sqm damp proof course

1 Answers  


WHAT SHOULD BE THE THICKNESS OF CEMENT M-SAND MIXER IN BETWEEN TWO SOLID CEMENT BRICKS USED FOR A HOUSE WALL?

4 Answers  


What should be percentage of silt content in sand?

11 Answers   TCIL,


What is the full form of APVC Pipe?

1 Answers   GSECL,


please know me that required quantity of cement , sand , water and bricks for 1 cub meter of brick work

1 Answers   Nirman Consultants,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)