How to calculate cement quantity in m20 concrete
Answers were Sorted based on User's Feedback
M20 concrete means 1:1.5:3
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg = 8.22 bags
Is This Answer Correct ? | 14 Yes | 1 No |
calculation of cement quantity in m20 concrete
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg = 8.22 kgs
Is This Answer Correct ? | 4 Yes | 2 No |
whats the field test of cement,aggregate and water
Difference between pre-tensioning and post-tensioning.
wat is meant by aerocon bricks?
what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.
Power grids in two adjacent states(A&B) are interconnected. Can power grid in state A can be represented by Thevenin Equivalent Circuit. If not explain Why?
wat is the optimum mix design for M25 grade of concrete ? is the ratio 1:1.5:3.65 correct?
what is the effect of duration of earth quake on framed structures ?
what is the rate for per sqm damp proof course
WHAT SHOULD BE THE THICKNESS OF CEMENT M-SAND MIXER IN BETWEEN TWO SOLID CEMENT BRICKS USED FOR A HOUSE WALL?
What should be percentage of silt content in sand?
What is the full form of APVC Pipe?
please know me that required quantity of cement , sand , water and bricks for 1 cub meter of brick work