How to calculate cement quantity in m20 concrete
Answers were Sorted based on User's Feedback
M20 concrete means 1:1.5:3
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg = 8.22 bags
| Is This Answer Correct ? | 14 Yes | 1 No |
calculation of cement quantity in m20 concrete
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg = 8.22 kgs
| Is This Answer Correct ? | 4 Yes | 2 No |
yet i am not got any hallticket from aai junior excequtive exam.any one got application form from aai.
2 Answers AAI Airports Authority Of India,
how to manage interview fear? and speak in english?
How to find out kg per Sft ?
HOW TO CALCULATE THE CEMENT & SAND REQUIRED FOR 1SQM BLOCKWORK OF 200MM THICK?
what is the minimum and maximum water cement ratio
How do you calculate load bearing capacity of a waffle slab?
what is the formula of calculating number of bars?
How much actual % of wastage of steel.
How to do lineout of building
Can rice husk ash be used instead of coal fly ash for manufacture of clc/ foam concrete
Explain what is zoning permit?
What is the meaning of TMT on Steel rebars
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)