How to calculate cement quantity in m20 concrete
Answer Posted / jayaprakashsst
calculation of cement quantity in m20 concrete
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg = 8.22 kgs
| Is This Answer Correct ? | 4 Yes | 2 No |
Post New Answer View All Answers
Define What is a projection line?
pls mail some more tecnical qustions at msaranya2610@gmail.com
How to improve the strength of fly ash bricks to avoid corner damge? How to get the color lighter similar to normal concrete blocks/
how to calculate the rebar depth if forgot the foundation reinforcement (main steel)? is that any calculation or formula we have data sheet of supplier what depth what is the pull out capacity is mensioned in data sheet. if any IS code than its help full to me.
Define What is aggregate?
What is difference between limit state and working stress method? How it is applies in building structure.
What in bending moment, if a moment is free end of cantilever beam?
What is aggregate?
How to get MEP technical,instaaltion & testing data for interview?
what is raft foundation
What is the ratio of grades m5, m7.5, m10, m15, m20, m25, m30, m35, m40?
What is geopolymer based concrete?
how to calculate the dry wt of sand and cement for a required design mix?for ex:M20
what should be the PCC ratio to construct a plinth of (40x40x4)ft...??also its estimated cost??
How to fix toll charge for a particular vehicle at toll booths in a highway?