How to calculate cement quantity in m20 concrete
Answer Posted / jayaprakashsst
M20 concrete means 1:1.5:3
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg = 8.22 bags
| Is This Answer Correct ? | 14 Yes | 1 No |
Post New Answer View All Answers
How can we convert weight batch to volume batch for m30 mix
Determine the production capacity of a treatment plant for a city of 1,250,000 population. Assume the specific consumption per capita of 15ol/c/d, non-domestic water use of 30,000,000 m³/year, and UFW of 12%.
02. a. The diagonal of a 9 cube…………… 1 b. Surface area of 9 cube…………… 1 c. Volume of 1-3 cube …………… 1 d. Compressive area of 6 cube …………… 1 e. Top & Bottom face of a Cylinder/Cube is to be proper leveled to deliver the…………………………..…… properly.
please briefly explain calculating or estimating steel quantity for a RCC column?
Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft
what is cement wastage percentage in NHAI ROAD WORKS
how to calculate quantity of bricks in circular manhole with examples.
how to find quantity of concrete in PCC M15
how to caluclate sienerge qty in construction in ap
what is the percentage of silt in black cotton soil.?
What black man invented the clothes dryer?
why we use aggregate,sand with cement in concrete?
i have a interlock pavement work.i need to compact about 2000 sq metres of sub base grade c of thickness 15 cm.what is the amount of water required for compaction ??
Can inverted beams used in pipes during construction?
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting?