how to calculate dry density of cement,sand for mortar of brick masonry
Answer / mehar
Dry density of mortor = wet density x 1.33(33% of volume)
Explanation :
1:6 ratio of mortor for brick work,
Means (1 cement : 6 sand)
For cement :
Density of cement x 1/7 =?
For sand. :
Density of sand x6/7=?
For cement density = 1440 kg/m3
For sand demsity = 1600 kg/m3
Is This Answer Correct ? | 1 Yes | 0 No |
what is poissons ration of steel?
how much cost of single coat 20mm thick plastering per sqre meter
Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
16 Answers Reliance, Siddhi Constructions,
What is PQC. Means PQC
14 Answers Era Infra Engineering, L&T,
how to design paver block
For a RCC section with congested reinforcement , what is the compaction factor
2 Answers Arihant, GMR, Gulf International Contracting, NBCC,
what is the ratio of m50 grade in concrete block
what is the load capacity of bored pile pile dia 500mm
In a given rcc design, how to calculate quantity of steel, for all practical purpose of construction?
9*9m 1:4:8 ratio using what quantity of 40mm aggregate, sand&cement please tell anwser
why will provide chair in slab
If the first roof slab is not deshuttering in this time shall I start column raising work in second roof is it correct or not
2 Answers Al Fara, Unity Infraprojects,