In beam where lapping is allowed for top and bottom bars?
Answer / nilesh kulkarni
A)For Top Bars lapping zone is at L/2 of Clear span i.e In To In distance betn supports.
B)For Btm Bars lapping zone is at L/3 of Clear span.
| Is This Answer Correct ? | 11 Yes | 3 No |
m15 screeding concrete ration calculation
How much quantity of cement,sand,stone used to build 1 cum of cc road??
0 Answers Pandey Construction Company,
Brick work how many days curing and at any concreting pl
use 1:1.5:3 concrete footing size 9'9" *9'9" and square 12" and also trapezoidal 22" use of 4 columns. calculate how much amount f concrete use. and also tell me the details about course aggregate and fine aggregate and cement bags use .(note; 20mm coures aggregate use)
if the nitrates more than 45mg/l in water lead to disease then what is it called
bridge design
what is mean by tremie concrete
How to calculate quanty of steel in four leg stirrups?
what is pile foundation?
HOW CAN DESIGN LENGTH,WIDTH AND HEIGHT THE FOUNDATION FOR THREE FLOOR BUILDING?
how much shouid be the rate for ready mix concrete per cubic meter
how much bags of cement will be in 1 cmt of having the ratio 1:3:6
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)