how to calculate the quantity of material in 1 cubic meter Concrete?
Answer Posted / kashif khan
Qty of concrete= 1 cum
wet volume = 1 cum
Dry volume = 1*1.54 = 1.54
First of all we calculate the ratio of concrete e.g 1:2:4
2nd step; Sum of ratio = 1+2+4 = 7
Qty of cement = 1/7*1.54 = 0.21999 cum/0.035 = 6.2854286 bages
Qty of sand = 2/7*1.54 = 0.44 cum
Qty of crush = 4/7*1.54 = 0.88 cum
| Is This Answer Correct ? | 17 Yes | 0 No |
Post New Answer View All Answers
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
what will be the cost of thickness of 125mmor rcc measurement of 52x33.75 feet
what is called the inverd level of mabhole chamber?
Prepare a Schedule for a Highrised building from starting stage to Handover?
How many square meter can mason layout chb per hour
What is the best type of wood glue?
Define different types of roof systems?
Explain what are the phases inspections are done by local authority while construction?
What is diversion tunnel in a dam?
how to do cementicious paint for rcc walls of cw pump house
What is the mix propotion of M10,M15,M20,M25,M30,M40,M50.M60 cement content,aggrigate,sand and water ratio.
In reclamation works what are the importance of geotextiles and sand?
Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??
cement and sand required for one block of size 0.23*0.15*0.46
column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial