It is not fixed as there are bricks of different size like nominal bricks , standard bricks , actual bricks each have varying size , so the volume of single brick must b calculated and the total volume must b divided by volume of single brick which gives no. Of bricks required ..
For nominal size its 500 per cu m

Correction-in your que you asked for sq m but bricks are never calculated for sq m they are calculated for cu m.

Is This Answer Correct ?    8 Yes 1 No

How can we calculate the no.of bricks per sq.mr?..

Answer / devipriya.m

500 bricks

Is This Answer Correct ?    11 Yes 6 No

How can we calculate the no.of bricks per sq.mr?..

Answer / azree

550 pcs of brick per m2 of single brick wall. Or its 1100pcs of brick per m2 of double brick wall

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

what is the measure of slump

9 Answers  


What is the best mixing ratio of concrete materiloas for raft foundation?

1 Answers  


How and where from do we get 162 for calculating sectional weight of TMT

1 Answers   Ankit Metal Power,


if L*B*H = 20 then direct no of bricks =20 *500

2 Answers   L&T,


in a mix if desired concrete slump is not obtained , the adjustment of each concrete slump difference is made by adjusting water by which percentage

2 Answers  






what is 43 and 53 grade of cement? that 43 & 53 represents what?

8 Answers   L&T, Saint Gobain,


what is the water cement ratio? how to calculate it? list the wt. of constructions materials including concrete both ordinary and light wt. concrete

0 Answers  


Write down a formula to calculate the number of 50Kg bags of cement for moulding of cement blocks of tcm thick by 20cm high by 40cm long on site with a mix ratio of 1 bag of cement to 3 wheelbarrows of sand . the sand is measured at a STRUCK( WATER LEVEL) 65 litres capacity wheelbarrow. TEL: +237 674630019

1 Answers  


Kindly tell me how much extra steel bars are provided in a RCC roof and distance of bends in different sizes of roofs. Please also tell me that bars provided in chajja are taken seperate or main bars or short bars are extended in chajja. please send me the answer@ suhail_akhter@hotmail.com

2 Answers  


which I.S. code shown wastage in structural steel

1 Answers   ITD,


i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?

0 Answers  


Will going from a 3-tap to 6-tap increase water pressure?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)