In barbending schedule why is o.42*D is taken. Means why o.42 only???
Answer / arghya das
that is 1.42d-d=0.42d
(1.42d comes from 1/sin45) 45 degree crank bar.
Is This Answer Correct ? | 4 Yes | 0 No |
can we find any technical issue if we are gong to change the dimensions of steel beams from one type to another type IE if there are any equievelant data base to find solution for problem of changeing sectios of beam from one type to another with the same cross sectional area.
what are the types of bridges respective to the span ?
What is an object snap mode?
how to calculate no of rings in columns & weight of column rings & column ?
concrete cube strength if fail 1 no in 7 days .What is the solution
What is bylayer?
how to calculate the steel for beams and columns for tender purpose? any formula have?
What is the actual formula to calculate dry consumption of 1cubic meter m20 Concrete???? Plzz tell seniors it is urgent..
plz tell me one brick total plaster area?
9 Answers Aparna Constructions, Aparna Enterprises, L&T,
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
what is unit of density,specific gravity
how many types of survey and what are levelling instrument?