In barbending schedule why is o.42*D is taken. Means why o.42 only???
Answer Posted / arghya das
that is 1.42d-d=0.42d
(1.42d comes from 1/sin45) 45 degree crank bar.
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
how to disign cuplock shuttering and it's matireal requirement snd any related web site
Define different types of roof systems?
Why steel rods are produced only in even dimensions?
In block work seawalls what is the purpose of slip joints?
how many material required for brickbat water proofing of toilets.
what is the formula to find the sttel (bar)length in beam having bent up at l/4 t 45 degree & 60 degree.
what s the standrd size of pvc fittings ,like elbow, bend,tee etc ? please explain with figure ?
what is the types of door's wood?
Howmuch bend to be provide for 200/600 BEEM
how can we construct building without foundation providing only grade beam at ground level
how water proof chemicals act in concrete to avoid leek?
Suppose you planning to paint newly fabricated workshop building made of structural steel of 10 tons total mass. How many litters paint primer for 1 coat and 2 coat of top coat?
how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend
Wat is meant by Aecron brick?
States some of the tool bars used in cad?