Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


why the secondary current transformer cannot left open



why the secondary current transformer cannot left open..

Answer / subbu

Since ct is step up transformer ,with secondary open , very high voltage will develop on secondary side. Due to this high voltage , secondary winding insulation will fail .this will lead to damage of secondary winding.

Is This Answer Correct ?    8 Yes 1 No

Post New Answer

More Electrical Engineering Interview Questions

what is the abbreviation of MIMIC regarding control and relay panels of power systems????

1 Answers   Enercon,


in single phase we get 220 volt and in three phase 4420 v why this second Ques= in case three phase star conection our neutrul becom disconect what happan 3 Q=== a three phase house load and have unbalce load on different pahse diffrent current eg phase a 7A b 8A c 5A and voltage is 440 than how calculate it total load in kw pl give formula thanks

8 Answers  


what is relay multiplier

1 Answers   Atomic Energy Commission, Bhel, Wipro,


could anybody able 2 send me jindal steels previous papers fr electrical steam....pls send 2 my id if possible....sirisha.shaik@gmail.com

0 Answers  


how to make neutral to ground voltage less than 5v? my house is under the high voltage transmission line so,proper grounding using rod salt n coal doesnt help me..so wat i do as i cant operate my computer ..this high voltage cause great problem to the motherboard i already two times replaced it.in my house voltage is coming near to 25 v between ground and neutral.plz kindly post ur answer to my email id manish77777@gmail.com ..

3 Answers  


what is post close & pre close of trip circuit supervision relay in circuit breaker control scheme?

2 Answers   ABB, NEK, Power,


what is the difference between 50 hz freq. and 60 hz freq.? which is better and economic in them ?

0 Answers   Faurecia,


why are you use the crgo core lamination in transformer

6 Answers  


if we apply 1000ADC instead of 100ADC or We apply 50ADC instead of 100ADC,What will be happened in the test result value.Pl explain

0 Answers   NCC,


Please tell me if you are electrical engineer,and you are appointed for the maintainance of Electrical Power plant,then which parts of the plant deal with you.Also tell how these parts/components work.

1 Answers  


what is size of 3phase 4wire cable to be used for 11 ton ductable A.C and how to calculate cable size for different load

0 Answers   Tata Power,


Advantages of short circuit and open circuit tests of a transformer?

3 Answers   Engineering,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)