how many bags of cement,sand and Aggregate to p.c.c. of 1:2:4
ratio.
Answers were Sorted based on User's Feedback
Answer / venkat@sarwan
Ratio 1:1.5:3 =5.5
1/5.5 * 1.54 =0.28
Cement 0.28 * 28.8 = 6.33 bags...
Sand 0.28*1.5 = 0.42 m3
aggregate 0.28*3 = 0.84 m3
| Is This Answer Correct ? | 2 Yes | 2 No |
Answer / aamir
1 bag pf cement is 35 litres. on stie we take aggregates by
volume so
fine agg=2*35=70 litres
coarse agg=3*35=105 litres
| Is This Answer Correct ? | 0 Yes | 1 No |
undisturb samples are obtained by direct excavation thin walled sampler thick walled sampler none of this
Explain what are the phases inspections are done by local authority while construction?
Quality of first class bricks
wat is meant by aerocon bricks?
HOW WE WILL CALCULATE QTY. OF CEMENT,SAND & AGGREGATE (10MM&20MM) IN Kg.
4 Answers Nagarjuna Construction,
How much cements bag (or in KG) required for 1 Sq. M concrete, for M-30 grad concrete as per CPWD and where is thr proof on site
How many square meter can mason layout chb per hour
what is meant by structural design
What is the likely strength of a 1:2:4 concrete mix?
if rise and tread of stairs rae 16 & 25cm with landing slab of thickness 100mm . If there are 8steps, and carpenter ask for to mark the bottom of centering of landing on column, what will be the height above floor finished level?
In Residential home construct footing,beam, column,lintel,rcc roofs which dia rod used how to self assumed
how can we differentiate the KOTA STONE and SHAHABAD STONE by vision?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)