L&T APFC Relay model etacon L8 fault:
Initial power factor is 0.6
when capacitor is on, the value of power is getting down,
please let me know the reason and rectification details.
Answer / ramesh
L&T make etaCON L8 CAPACITOR BANK plant running time pf ok, plant shutdown time using 50nos tube light load pf 0.257,The capacitor bank not in service, programme procedure connect capacitor 5kvr
| Is This Answer Correct ? | 8 Yes | 0 No |
pls send me the syllabus questions on rrb section engineer (telecom)
on what basis hardware and software interrupts are defined
What is meant by mcmurray inverter?
What is angle and amplitude modulation?
is there a way to us 2 dstv smartcards with one subcription at once?
Please send me the sample pattern for the Electronics and communication for the post in RRB s&T to my Email ID : sivamec6034@gmail.com
what is the expansion of DSP?
15 Answers HCL, TCS,
what are the conditions of fs=2fm?
also send me aptitude question paper
please send the latest sample question paper for the hal online test for electronics stream
pls send my id for supervisor model paper qustion
name the type of AM used in TV picture transmission and why is it used ? draw the frequency domain spectrum of the TV signal
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)