L&T APFC Relay model etacon L8 fault:
Initial power factor is 0.6
when capacitor is on, the value of power is getting down,
please let me know the reason and rectification details.
Answer Posted / ramesh
L&T make etaCON L8 CAPACITOR BANK plant running time pf ok, plant shutdown time using 50nos tube light load pf 0.257,The capacitor bank not in service, programme procedure connect capacitor 5kvr
| Is This Answer Correct ? | 8 Yes | 0 No |
Post New Answer View All Answers
the number of factors of 576?and the logic for this question?
why cristal frequency is different in microcontrollers and crystal oscillators?
Explain why are using 4ma to 20ma for signal transfer. Why not 0 to 20ma?
What is meant by retrace time?
What is meant by load commutation?
What are active & passive elements in BTS?
what is the difference between DVB-S& DVB-S2
why sometimes PF value have an negative sign?
Why the width of the base region of a transistor is kept very small compared to other regions?
explain double side band and double side band -substrace carrier
What is a bcd? What are its advantages and disadvantages?
What is the effect of polarization of dielectric under heat?
Explain how to identify how many states the ripple counter is having by looking at the figure as it can also have some invalid states?
Which type of connector we use at the end of GSM antenna/
Why iceo >> icbo?