L&T APFC Relay model etacon L8 fault:
Initial power factor is 0.6
when capacitor is on, the value of power is getting down,
please let me know the reason and rectification details.
Answer Posted / ramesh
L&T make etaCON L8 CAPACITOR BANK plant running time pf ok, plant shutdown time using 50nos tube light load pf 0.257,The capacitor bank not in service, programme procedure connect capacitor 5kvr
| Is This Answer Correct ? | 8 Yes | 0 No |
Post New Answer View All Answers
what do you mean by quasi fermi level?
HI ALL.. I TOO APPLIED FOR THE POST OF JR.EXECUTIVE ELECTRONICS(AAI).HOW DO U PEOPLE KNOW ABOUT THE EXAM DATE DO U GOT ANY ACK...
Which is the pin no of CN1 TERMINAL and the parameter using in delta servo drive for auto/man input and start forward input
What are the different methods of firing circuits for line commutated converter?
Why signalling link load should be less than 30% in telecommunication?
what is inductive couplers
How many RRI we can use in One BTS?
what is firing angle of phase controlled rectifier?
What are the applications of buffer?
What is the difference between CAT 5e communication cable & CAT4 Communication cable
For a 1φ voltage controller, feeding a resistive load, draw the waveforms of source voltage, gating signals, output voltage and voltage across the scr. Describe the working with reference to waveforms drawn?
what is the purpose of joining engineering?
Tell me why bjt is called current control device?
hi friends.any one tell me pattern for mt exam for steel plant..plz plz plz..
1 *2 1*3 *2*4 1*3*5 *2*4*6