How to calculate the quantity of cement,sand,aggregate for the area L*B*T
are 15.24 m*21.36m*0.12m in the ratio 1:2:4
can any ine explain in detail by using formulas.
Thanks in advance
Answers were Sorted based on User's Feedback
Answer / karthik rajendren
Volume of Concrete = 15.24*21.36*.12 = 39 Cum
For 1:2:4 , Req.Cement Bag = 6.46 Bag/Cum , Sand = 0.44 Cum
, Agg =0.88 Cum.
For total Requirement,Cement = 41*6.46=264.86,Sand =
.44*41=18.04Cum,Agg=.88*41=36.08 Cum
(5% wastage's for Concrete is considered)
| Is This Answer Correct ? | 9 Yes | 6 No |
Answer / navjeet kumar
mixed grade 1:2:4(cement:sand:aggregate)
sum=1+2+4=7
volume of concrete=15.24*21.36*0.12=39.06cum
requirment of cement=(1/7)*39.06=5.58cum
requirment of sand=(2/7)*39.06=11.16cum
requirment of aggregate=(4/7)*39.06=22.32
you can check right or wrong by =5.58+11.16+22.32=39.06cum
so right
| Is This Answer Correct ? | 1 Yes | 2 No |
Concrete how muvh strenght gain 7days,14day,s,21day's,28day's&56day's after curing
How many types of traps are used?
wat happens to the foundation when only live & dead loads are considered( wind load is excluded) during the design of tall structures. options are: a)only settlement in the internal structure and not external structure b)only settlement in the external structure and not internal structure c)no differential settlement d)none of the above
4 Answers BBJ Construction, IOCL,
explain how to calculate top and bottom diagonals for transimission line tower foundation with prop setting
m25 water cement ratio calculation
beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?
Why can i adopt concreting insted of rubble solling in beds? In comoarision concreting is cheaper than the soling.
what is mean by stripping?
Sir please Bhel Enigineer trainy test papaers in civil engineering
2. What are the grades of steel used in the concrete design?
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
what is the amount of absorption of slurry in shuttering ply board. what is the amount of slurry leakage allowed for 1 m3 of concrete.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)