How to calculate the quantity of cement,sand,aggregate for the area L*B*T
are 15.24 m*21.36m*0.12m in the ratio 1:2:4
can any ine explain in detail by using formulas.
Thanks in advance
Answer Posted / karthik rajendren
Volume of Concrete = 15.24*21.36*.12 = 39 Cum
For 1:2:4 , Req.Cement Bag = 6.46 Bag/Cum , Sand = 0.44 Cum
, Agg =0.88 Cum.
For total Requirement,Cement = 41*6.46=264.86,Sand =
.44*41=18.04Cum,Agg=.88*41=36.08 Cum
(5% wastage's for Concrete is considered)
| Is This Answer Correct ? | 9 Yes | 6 No |
Post New Answer View All Answers
what is Bearing Capacity,How to determine it?
How many hours should traffic be not allowed after completing wbm road or bst.and min how many hours should road rollers be used.
Iwant to calculate the production of 1 labour for concrete casting which includes shuttering,scaffolding,steel fixing,concreting, deshuttering and curing in 8hours.But i am not able to determine it approximately would you pls.??
what is the procedure involved in preparing mix design of m15 grade as per IS-10262-1982
what is grade intersection?
what is the relation between pitch of steel and depth of slab?
What out turn civil works
cement mortor 1:5 for 30 m2 12 mm tk plastering so how to calcualte its rate
what is stressing
we have a bore well 275 depth & water is deliver at distance of 1000 feet from the borewell here iam not include the distance of depth and the deliver water horizontally at our reserviour tank on ground level
what is the max. and mim. height of vertical post in informatry sign board which is used in highway projects.
What is the difference between absorption & adsorption and sorption?
how many digree of freedom in four bar chain
What is the name of this multiplication factors ?
Dear Frds, How can i calculate the Steel for RCC Slab, Please provide one Example also, so that i can understand very well. Ex: Area: 1320.0 Sft.(44' X 30') Span: 15'(Default). Column Size: 9"X15"(6 No.s 12mm Rods) Please Provide Calculation Details. Thankyou. Satish