Answer / yogesh jadhav
m15(1:2:4)
100cum given
wet volume of concrete=30%more than dry volume
=1.3*100=130cum
wastage=20%of wet volume of concrete
=1.2*130=156cum
volume of cement required=156cum/1+2+4=22.28cum
1 bag of cement=35 lit=0.035cum
no of cement bags required=22.28/0.035=636.57=637bags
sand rqd=2*22.28=44.56cum
coarse agg reqd=4*22.28=89.12cum
Is This Answer Correct ? | 24 Yes | 5 No |
Answer / sjtbehera
For3 100 cum
Aggregated- 88 cum
Sand-44 cum
Cement- 22cum. 660 bag
Is This Answer Correct ? | 18 Yes | 7 No |
Answer / channa
1m3 of dry concrete = 1.54m3 of wet concrete
Concrete work to be done=100×1.54=154m3
Cement=(1/(1+2+4))×154=22m3
Wkt, density of cement=1440kg/m3
Mass of cement=1440×22=31680kg
No of cement bags= 31680/50=634bags of cement required
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / vishamvar
For 10cum of M15 (1:2:4)
concrete 15.2cum dry weight
is require thus
for 100cum concrete
approx. Quantity of material
will be
Cement = 21.71 cum
Sand = 43.43 cum
Aggregate = 86.84 cum
Is This Answer Correct ? | 5 Yes | 3 No |
Answer / ajit kiling
For 100 cum work
For m15 grade of concrete (1:2:4)
Dry mortar of 1cum =1.54cum For 100cum= 100*1.54
= 154cum
Cement=154/(1+2+4) = 22cum
Sand= 22*2=44cum
Aggregate=22*4=88cum
Is This Answer Correct ? | 2 Yes | 0 No |
what is the I.S. CODE of RCC
how do i find the fixed end moments in the fixed beams with the use of general method?
04. a. Slenderness ratio…………… 1 b. If the height of a stage is 15-0 & dia. of the prop is 5, the slenderness ratio is….… 1 c. If the height of a stage is 10-0 & dia of prop is 3, the number of bracing will be…… 1
Detection of a beam & a girder are––––
how did find the quantity of cement ,sand , and aggregate in concreat which is givan by volume
when we workout quantities of reinforcement steel , whate are the critari of lap length for column
What is gravity flow?
which type of foundation are most prefarable in blockcotton soils
What are the benefits of rcc pipes over steel designed pipes?
Used Cement & Sand in 1 Square Meter or 1 Square Feet For Brick Work 0.115mm ? (1:4) (1:6)
0 Answers L&T, Shoba Devlopers,
how to calculate the steel in 500yard
how to absorb to site basic corrections? which are the important correction?