100 cubic meter of concrete will contain how much amount of
cement, sand and aggregate to form a mix of M15

Answer Posted / channa

1m3 of dry concrete = 1.54m3 of wet concrete
Concrete work to be done=100×1.54=154m3
Cement=(1/(1+2+4))×154=22m3
Wkt, density of cement=1440kg/m3
Mass of cement=1440×22=31680kg
No of cement bags= 31680/50=634bags of cement required

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What do you mean by honeycomb in concrete?

700


I have an span length 16 ft c/c

1049


use ofr concrete as per grade ?

1628


what is the use of water bar in water tank and is this an extra item in estimate?

2104


quantity of material needed for rubble stone masonry for 1:4 and 1:6

1208






how to control PQI (Project Quality Index)

9799


what is the types of surveying?which type of survey carrying for type of work?

1661


Minimum and maximum size of the building components

1760


What black man invented the clothes dryer?

675


How you can turn off the display for dimension in CAD?

625


What are the uses of groynes?

665


why demand factor less then 1 ?

1759


What is aggregate?

713


How is the leaning tower of pisa supported?

634


How much cement is require in one sqft area in a G+3 residential construction.

1581