Answer Posted / k r kumar ranjan
Normally In Coal based thermal power plant(Either Sub or Super Critical) 60% Bypass is adopted based on condenser heat load calculation keeping 0.9 as Condenser Cleanliness Factor.
If Some designer wants to bypass 100% of generated steam, it is also possible. In fact most Nuclear Steam Turbine adopt same for same reactor shutdown process.
Increase in % capacity of bypass system increases capital cost involved in condenser cooling surface, Extraction pumps, LP Heaters, Pipe Sizing etc.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
what is the trip circuit supervision in an electrical meaning?
some one can tell me how residual type excitation is provided through transformers to an AC generator without any battery or PMG&excitor
our 125 kva DG does not start in AUTO mode works normally in MANUAL mode please give me a solution.....
By any way can we increase the B check hours from 300 to 500
How to calculate boiler capacity? I have 1 Autoclave, Which has to use for AAC block. Dimension for this Autoclave is - 13 Meter Length & 2.2 Meter Diameter.
What is surging in a centrifugal compressor ? How it occur's ? How is antisurging done ?
what does mean by kva rating
operation
DCS marshaling Cabinet Power supply can be replace during plant running time? Answer Yes it is possible. I am talking about the controller and cards power supply modules. They are always redundant and connected through diode so that if one power supply fails the other can take the charge immediately.so it is possible to replace one of them in running plant if the other one is healthy. MY question is how switching done.
why airtel use + 24 volts and other operators use -48 volt
Looking for Bently Nevada surplus 3300/52-01-00-00 Reverse Rotation Monitor , 4 pieces.
Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon
explain how the third harmonic content of the magnetising current affects transformer design
what is restricted earth fault explain in details
im try to calculating seawater flow required for SW-FGD system. I need a guide, equation or method to do it, can some one help me! Thanks very much