Density of concrete is 2240-2400 kg/m3.
Density of steel is 7860 kg/m3.
The Pycnometer can be used for determination of the specific gravity of solid particles of both fine grained and coarse grained soils.
As the moisture content of a fixed weight of sand increases, the volume also
increases--up to a point. This is known as bulking of sand.
An under-reinforced beam is one in which the tension capacity of the tensile reinforcement is smaller than the combined compression capacity of the concrete and the compression steel.
An over-reinforced beam is one in which the tension capacity of the tension steel is greater than the combined compression capacity of the concrete and the compression steel.
A balance section is one in which the concrete crushing and steel yielding take place at the same time.
| Is This Answer Correct ? | 8 Yes | 0 No |
Answer / lalit madnawat
Density of concrete=2400 kg/
cum.
Density of r.c.c. =2500 kg/
cum
density of steel = 7850 kg/
cum
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / suresh bariya
Density of Concrete 2500 Kg /M3
Density of Steel 7850 Kg /M3
It is the phenomena of the increase in the valume of sand
due to water on the surface of sand is called Bulking of
sand.
| Is This Answer Correct ? | 3 Yes | 1 No |
What is the life of anaerobic Digester if it is used for municipal solid waste digetion.
what is permissible IRC limits of silt content in river sand in India
granite tiles laying 60/sq ft.how to convert in sq mt,what is the mltiplying value.
the beam size (450x1000) effective length is 19.0mts no intermediate supports and top 8nos 32dia and bot 32dia and condition is stragge lap. it is exceeding lap zones and exceed length of bars?
what will happen if one could not properly follow the spacing of slab reinforcement bar?
0 Answers Yirgalem Construction,
what is the ingrediants of wet mix macadam?construction procedure?
1:4:8 pcc calculation 591 cu.ft
GIVE US YOUR FULL DETAIL OF THE FOLLOWING… FULL NAME.. PERMENENT MAILING ADDRESS DIRECT CONTACT NO E MAIL ADDRES.
how much quantity of work we can get by rod benders per day
where does the hinged action while designing the strture
how to calculate sump capacity
2 Answers AVS, KMC, Personal Assistant, Shrey Associates,
What is the amount of cement,sand and course aggregate(jully)(in kgs) required for the RCC of an area of 450 square feet and 5 inch depth if the concrete mixing ratio is 1:2:4(cement:sand:jully)?your answer will be very helpful.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)