Siporex Block Work has 0.18/sqm of cement consumption whereas
Plastering Work
a)External Plaster 1st coat 0.13/sqm
b)2nd coat comprising of 0.08/sqm,
c)Internal Plaster has 0.13/sqm.
Is This Answer Correct ? | 4 Yes | 0 No |
what is thumb rule exactly?
What are the various load combination in Limit state method?
2 Answers Developer Building Contracting, DMRC, Engineers India Limited,
How much quantity of rod binding work by a rod binder per day
How much quantity a carpenter can do in a day
How can u prepare mix design for concrete?
How you Confirm the Hard stratum for Driven cat in situ Pile work?
How to find weight of steel in kg if we know the area which is in m2? Following details are known to us, Area=125m² thk of slab=250mm Steel details:T12@200 PS:considering mesh top and bottom with X and Y direction
What's the expanded form for NMR?
the coefficient of curvature for a well graded soil must be inthe guage 0.5-1 3-4 4-5 none
how many materirials in 1 m3 concrete
Can anybody help me by attaching files , formats for quality checks of common building materials like cement , concrete , bricks , sand and aggregates? Regards,
45 Answers CDS, L&T,
What is the difference between Normal Concrete and High density concrete?