Siporex Block Work has 0.18/sqm of cement consumption whereas
Plastering Work
a)External Plaster 1st coat 0.13/sqm
b)2nd coat comprising of 0.08/sqm,
c)Internal Plaster has 0.13/sqm.
| Is This Answer Correct ? | 4 Yes | 0 No |
how many blocks will come per 1 meeter squear
what is drainage system?
Which tests are performed on soil to decide the type of foundation to be provided.
what are the types of flow? what is terbulent flow?
use ofr concrete as per grade ?
Why curing is necessary for concrete
we do not provide reinforcement bar through the centre of a column.why?
How much quantity of coping is done per day by one mason in Rmtr?
What is the outturn of Ceiling plastering
what is education Cess.
What Are The Steps Involved In The Concreting Process, Explain?
What is the standard unit of bricks???
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)