Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


What's the difference between cold loop test and hot loop test?

Answers were Sorted based on User's Feedback



What's the difference between cold loop test and hot loop test?..

Answer / ravi

1.Cold Loop Check 
This is an electrical continuity check to confirm wiring integrity from control panel's terminal block to the field instrument. Please note that field cabling starts from field instrument and goes through Junction boxes and marshaling cubicle to reach termianal blocks of the control panel 




2.Hot loop check 
After successful cold loop check, each I/O is subjected to hot loop check. In this testing entire loop functionality is checked by simulation of the signal with power up from DCS or PLC 
1.Calibration range 
2.Activation of inputs / outputs / Field switches / Solenoids 
3.PLC/DCS register updates 
4.SCADA updates

Is This Answer Correct ?    102 Yes 2 No

What's the difference between cold loop test and hot loop test?..

Answer / jain

Cold loop check may also called as continuity test, to identify weather the cable are terminated at its correct terminal blocks from field side instruments to Control panel. At this time no power is present in the loop, or it may be isolated from the power source. It can be done using a Multi meter.

Hot loop check is done after cold loop test to identify the instrument is at correct range, units, and its dependency with the control instrument. so can be change and calibrate using a communicator or manually while the instrument is energized from the panel by 24 volt or vice versa.

Is This Answer Correct ?    11 Yes 0 No

What's the difference between cold loop test and hot loop test?..

Answer / hasan

Cold loop checking = continuity test, ir test make sure the cables are damaged or un damaged

Hot loop checking = instrument functionality test its means the instrument is in running condition if any fault may occur r not its should be make sure

Is This Answer Correct ?    5 Yes 0 No

What's the difference between cold loop test and hot loop test?..

Answer / ajinkya

I think...
Cold loop test is done using simulator
Hot loop test is done actually in field

Is This Answer Correct ?    6 Yes 63 No

What's the difference between cold loop test and hot loop test?..

Answer / jaydip khatri

hot loop mean instrument to J.B. & cold loop mean J.B. to panal.

Is This Answer Correct ?    5 Yes 73 No

Post New Answer

More Instrumentation Interview Questions

How to Calibrate Flammable gas detector in field

0 Answers  


Sir i am studying M.sc,(Tech.)Electronics and Instrumentation in Andhra university.What is the offers for me?

4 Answers  


How to Calibrate Ultrasonic Level Transmitter in field

0 Answers  


pt range is -45 psi to 45 psi.friends can you give answer with calculation and with linerity scale like 0%,25%,50%,75%& 100%?

1 Answers   WB,


i have one temperature TX in my loop check time once i was remove elament temp gose maximum then i am conect corectly but still now temp showing maximum what can i do this problem?

2 Answers  


i want interview questions about PROCESS CONTROL INSTRUMENTATION , SENSORS AND TRANSDUCERS IF ANY BADY KNOW ABOUT THAT PLEASE SEND TO MY MAIL karumudi1003@gmail.com

8 Answers   Honeywell, Reliance,


I want to know if flowrate increases in 16' pipe line what will happen to upstream pressure and why?

1 Answers  


pls send me the 10 years technical question papers of NTPC AND BHEL

15 Answers   Bhel, NTPC, ONGC, UCE,


What is seismic transducer?Where it is used?

1 Answers  


Profibus DP is a multi-master system. Would it work on RS-485 4W or not, and justify your answer

1 Answers   EIT,


I have completed B.E. Instrumentation & control in 2009. i have 3 year industrial job experience in chemical plant.now, I want to join M.E. in external. so, Plese say easiet way and good institute name.

0 Answers  


please tell no. & add. of consultancy who recruit me in power plant as instrumen engg. present i m working in power plant as ass.t instrument engg. thanku mahesh 09226562826

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)