We konw, Unit weight of cement = 1440 kg/cum
i.e. 1440/3.28^3 kg/cft
= 40.80 kg/cft
1 bag cement = 50 kg,
Then, 1 bag of cement = 50/40.8 = 1.23 cft = 34.72 litres
so none of above given options are correct.
| Is This Answer Correct ? | 13 Yes | 2 No |
Answer / engr.asad ali
Answer #3 is correct my first answer is wrong because i was
not concentrated fully on question but the above question is
right when we determined quantity of water with respect to
water cement ration
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / ratheesh
Its Nice Asad Ali.. i like your attitude.. (We can proud we
r a Civil engg)
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / nibas swain
Simple...
1 cum- 1000 lt
1 cum-1440kg
1440kg=1000lt
50kg= 1000/1440*50= 34.72 lt
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / engr.asad ali
Quantity of water in mortar and concrete depend upon on
water cement ratio see
we know that
W/C ratio = Quantity of water
--------------------
Quantity of cement
when W/C ration is 0.54
then
Quantity of water for one bag is 27 lit
when W/C ratio is 0.494
then
Quantity of water for one bag is 24.7 etc
| Is This Answer Correct ? | 4 Yes | 6 No |
How to hide dimensions in autocad?
How is improve my knowledge in construction industries....
In Earth work compaction How u calculate How many liters of water required,for compaction of ordinary soil for one Cu.m.
WET BULB TEMPERATURE AND DRY BULB TEMPERATURE?
what is meant by MIS report
The designs required to construct a building are ––
What are the tests conducted on coarse aggregates ?
how much dry volume of cement in 1cum in m20 grade
Time required for curing of wall tiles before fixing
what is the out turn of one masson in plastering, masonary work in 8 hours, with limited healper? what is the out turn of corpender in form work? wood work? in 8 hour with limited healper? what is the out turn of bar bendarin 8 hour with limited healper for slabs, beams, coloumn?
Explain what is alternate bid?
what is bond strength of concrete
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)