what is the out turn of one masson in plastering, masonary work in 8 hours, with limited healper? ..

Answer / guest

10 SQM PER DAY ,1000 NOS DAY,

Is This Answer Correct ?    15 Yes 7 No

what is the out turn of one masson in plastering, masonary work in 8 hours, with limited healper? ..

Answer / ravi

1)150to180Sft or14 to 16 Smt 2)formwork 600Sft of roof
shutering
or 112 Sft of plain door shutering
3)slab 1200Sft
beem 1.2 Ton
column 1.3 Ton

Is This Answer Correct ?    11 Yes 7 No

Post New Answer

More Civil Engineering Interview Questions

why we can use dust in concrete insted of fly ash

0 Answers  


What is the difference between built area and super built up area?

0 Answers  


What is different between DI Pipe and CI pipe?

0 Answers   DAE,


i need the how much materials are needed for cubic feet of concrete?

1 Answers  


if rise and tread of stairs rae 16 & 25cm with landing slab of thickness 100mm . If there are 8steps, and carpenter ask for to mark the bottom of centering of landing on column, what will be the height above floor finished level?

2 Answers  






How to arrive dry volume of concrete (1.52 to 1.57) ?

0 Answers  


How many required water of 1m3 Brick masonary and slab casting?

1 Answers   Everest Bank, GVR, Vijay Nirman Company Pvt Ltd (VNC),


How to Rectify deep crack formed on Brick Wall? Explain the method of rectify the defect?

3 Answers   Coromandel,


what is lap length? why it is required?

4 Answers  


1)How to calculate concrete cube testing load by area in mpa 2) in kg/cme also

1 Answers   SLEC,


In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?

0 Answers  


is basic cost of the material includes tax?

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)