if the length and breath of footing is 1.2m x 1.2 m what
will be the length and breath of foundation trench
Answers were Sorted based on User's Feedback
Answer / jt
1.2+extra width for pcc(.15) =1.35 wide and 1.35 length may
be sufficint for excavation bottom.
| Is This Answer Correct ? | 11 Yes | 3 No |
Am not agree with the above posted answer because,
as we all know you can not dig the exact paper size trench
practically on ground,
so, answer could be = length of Footing + extra pcc length
(if not considered then also its Ok)+ extra digging portion
(depends on excavater for its better working)
= 1.2 + 2 X 0.150 + 2 x 0.300
= 2.1m
So Length/Width of trench = 2.1 X 2.1 m
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / protin rabha
Not correct at all. We have to consider extra length and breadth for centering and shuttering also. At least 30 cm both side. So, if footing size is 1.2×1.2m then plus .30m extra both side. Which means size of foundation trench will be 1.5×1.5m. And PCC size can be taken as 150mm extra both sides, which will be 1.35×1.35m PCC size.
| Is This Answer Correct ? | 0 Yes | 0 No |
In Rcc ratio calculation I wanted to know quantity of Steel also.
What is the difference between Fe 500, Fe 500 D and Fe 515.
how can we determine the quantity of steel bars in a structure? is there any formula for determing the number of bars required ?
How we can calculate cement and sand for a wall 25ft x 28ft.Thickness of wall is 9inches.
Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?
how to calculate the size of triangular ring in rcc column?
0 Answers Prime Perfect Buildcon,
Define What is diversion tunnel in a dam?
What is bmc stands for in bmc software?
to construct 1450 rft length of 6 feet wall how much cement sand and blocks are required????
TELL US ABOUT A TIME WHEN YOU FAILED TO MEET A DEAD LINE. WHAT WERE THE REPERCUSSIONS?
what is smart building materials?
Define Finite element method (FEM)
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)