if the length and breath of footing is 1.2m x 1.2 m what
will be the length and breath of foundation trench
Answers were Sorted based on User's Feedback
Answer / jt
1.2+extra width for pcc(.15) =1.35 wide and 1.35 length may
be sufficint for excavation bottom.
| Is This Answer Correct ? | 11 Yes | 3 No |
Am not agree with the above posted answer because,
as we all know you can not dig the exact paper size trench
practically on ground,
so, answer could be = length of Footing + extra pcc length
(if not considered then also its Ok)+ extra digging portion
(depends on excavater for its better working)
= 1.2 + 2 X 0.150 + 2 x 0.300
= 2.1m
So Length/Width of trench = 2.1 X 2.1 m
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / protin rabha
Not correct at all. We have to consider extra length and breadth for centering and shuttering also. At least 30 cm both side. So, if footing size is 1.2×1.2m then plus .30m extra both side. Which means size of foundation trench will be 1.5×1.5m. And PCC size can be taken as 150mm extra both sides, which will be 1.35×1.35m PCC size.
| Is This Answer Correct ? | 0 Yes | 0 No |
What is a tensile strength? What is the tensile strength of wood?
What is the functional difference between DOME and R.C.C., where purpose of both covering roof?
How could I calculate quantities of fine aggrigates(sand) & coarse aggregates in pcc M15
1 Answers Coromandel, RECPDCL,
why steel is used in r.c.c why steel is used in r.c.c
Which one is the main bar in a square slab (2m x 2m)
10mm aggregate 1brass = How many KG
1 Answers JMP, Rathore Group, Trishul Construction,
Slump Values for works?
0 Answers Aditya Constructions, SVS Constructions,
What is thickness of RC hume pipes of size, 300mm, 450mm,600mm
What are the important hardware systems used for cad?
column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial
0 Answers Era Infra Engineering, Tricom,
the coefficient of curvature for a well graded soil must be inthe guage 0.5-1 3-4 4-5 none
How much block, cement,sand,is required for 1 sqmt of 200*200*400 block work
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)