how to calculate the capacity of CT operated LT trivector
meters on a particular distribution transformer.
Answer / prakash g.r.
In distribution transformer, the LV side voltage is 433V(LL)
or 230V(LN). The secondary of the CT provided in the DT is
may be 5 A or 1 A. Hence the capacity of trivector meter is
230V, -/5 A or 230 V,-/1A.( - stands for primary which
varies with capacity of DT (ie) 200/5A or 400/5A like that.
| Is This Answer Correct ? | 0 Yes | 0 No |
why there using acb enclosure in big buildings
what is zero sequence curr ent ?
what is let through energy of mccb
Why the ceiling fan rotates in clockwise direction and table fan rotates in anticlockwise direction.
3 Answers Kirloskar, MPF, Wipro,
What are the types of instrument transformer?
what is the max working temperature of an oil filled transformer say of about 1500kva.
HOW DEFINE THE IP FOR ELECTRICAL EQUIPMENT AND WHAT IS THE IP OF PANELS USING IN HAZARDOUS AREA ?
In order that work may be done:(a) Two wires are necessary(b) The circuit must have a switch(c) Coal must be burnt(d) A supply of energy is required
Why you want to join non technical field when you are an engineer?
What is the unit of attenuation?
Befor synchronissation of Generator what test to be carried out.pl.specify with reason.
How can maintain our H.T. motors used in cement plant. please send me procedure.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)