what are all the pre commissioning activities in WTP in
power plant
Answer Posted / rajan pandey
Raw water pump should be ready by which we can take
water to creator.proper cleaning of aerator,clariflocculator
And storage tank.Dosing system like alugm Dosing,lime dosing,chlorine
dosing should be commissioned.ReadyNess of flocculator.fitting scrapper
Fitting .isolation gate operations should be cheated