brick work with 1:6 cement mortar how many bricks and
cement and sand require for 1cum
Answers were Sorted based on User's Feedback
Answer / vijendrasinh
1 cum ratio 1:6
brick - 445 nos + 5 percent add.=500 nos App.
mortar 1 cum .30
cement= (1/7)*0.3=0.0428/.035=1.224 bags
sand= (6/7)*.30=0.26 cum.
Is This Answer Correct ? | 15 Yes | 2 No |
if brick size 240mm*115mm*71mm
so =0.00195cum
for full wall 25%(0.25)of mortar required
for half wall 30%(0.3)
if full wall means
req bricks=1-(1*0.25)=0.75cum
so=0.75/0.00195=384.6 no of bricks
req cement=0.25/(1+6)=0.0357cum
so=0.0357*1440=51kg
req sand=0.0357*6=0.214cum
note:prepare 15% extra mortar bcoz of voids presented in sand
Is This Answer Correct ? | 2 Yes | 0 No |
Answer / neel
for one cum 1: 6 cement mortar brickwork
Bricks:- 500 no
Cement:- 15 bags
Sand :- 2.5 cum ( .9 brass)
Is This Answer Correct ? | 3 Yes | 11 No |
How can I check the quality of sand,brick,and aggregateat site without using any labouratory test?
I used Etabs software to analyse a high-rise building. And I want to use templated UBC-codes inside to calculate the Seismic load. My question is: whether or not I have to control the seismic load by base shear load which is manual calculation? (just for more clarification: I can control this by input the scale factor into Eartquake definition in Etabs) I would highly appreciate your answer.
can you give me the details of rate analysis of steel and concrete?
how to know rcc strength
what is called camber in the road ?
Explain the advantages and disadvantages of using plastic and timber fenders?
How to calculate the compressive strength of 28 days of concrete where we have 7 days compressive strength?
What is the mixing of D.P.C?
how the centre of gravity is used in construction?
in 1:4,1:6 and 1:8 cement mortar mix how much water required? and find water cement ratio?
rate analysis for cement pointing 1:4 , for 100 sq m
What is the outturn of Ceiling plastering