Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

brick work with 1:6 cement mortar how many bricks and
cement and sand require for 1cum

Answer Posted / vijendrasinh

1 cum ratio 1:6

brick - 445 nos + 5 percent add.=500 nos App.

mortar 1 cum .30

cement= (1/7)*0.3=0.0428/.035=1.224 bags

sand= (6/7)*.30=0.26 cum.

Is This Answer Correct ?    15 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Is it necessary to apply tack coat over the primecoat. IF not what happens.answers other than 1.to superimpose the next layer(2) to adhere the layers so as to form homogenity.

1738


How to calculate sand , cement quantity for 23mm thk brick work(10x10)

5158


how many kg of 20mm, 10mm, dust available in one ton stone boulder

1853


What is the origin of name railway sleepers?

1316


what is diversion?

2184


If we have the center line of the Finnish road level and we want to know what level of pay would have offset the Lhs and Rhus RHS 1,2.5,5 1,2.5,5 m.

1985


asubmerged weir is one in which the water level on the down stream side of the weir is just at the crest level below the crest level above the crest level at stamp elevation as water surface on upstream

1920


undistributed samples are obtained by

2379


What goals do you have in your career?

2098


How much material is required for constructing a 2 Lane 2Km rigid pavement road

2175


What is the usage of zoom command?

1268


How and where are aqueducts built?

1188


contractor receive 100 MT steel.after compliting the work the contractor refund 90 MT steel.How reconsilation of steel done?

2317


significance of specific surface area of particles?

2093


what is spacing of wallar support of 3m column. the thickness of column is 0.25 m.

2372