I am getting diesel genset 62 kv for my house
In addition there are 6 meters of 11kv for the house
Lift also being installed for house plot sise 200sq yds
total 4 + 2 foloors
I want to know how much earthing required how deep it should be
Answers were Sorted based on User's Feedback
Answer / allwyn
4.5m deep g.i pipe along with 30 kg charcoal and 15 kg salt
| Is This Answer Correct ? | 1 Yes | 0 No |
required for dg set earth pits are 2 no,s of dg body, 2 no,s
of dg nutaral.
6 meters required to 6 earth pits and lift also required to
2 no's body earthing
| Is This Answer Correct ? | 1 Yes | 0 No |
1- What is the Polarization Index number be good for 15KV 3c#500MCM electrical cable? 2- Can I use the IEEE Std 43-2000 to perfom the PI test? Thanks
What is rotating magnetic field?Discuss elaborately.
CAn a TJM 10 relay measure over current ?
How to calculate meter constant @ HT yard
in which direction real power and reactive power flow and why???????
what are all the daily preventive maintainance carried out in transformer?
Explain what is electric traction? Explain few advantages of electric traction system?
what is working parincipal of a ht transformer
Why Phase to Neutral get spark
why only 26v dc is used in aircraft and 115v ac in aircraft.
Which test will be more severe for VCB?
FLP zone Types and Details
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)