how to find out the quantity of cement sand and aggregate
in slab and flooring
at first volume i.e lenght ,breadth , hieght
den for eg.
a) For 1 m3 of concrete Mix 1:2:4 (M15)
Add 50% for wet concrete = 1.50 m3 or 1.52 m3 or1.55 m3
= 1.50/(1+2+4) = 0.214 m3
For 1 m3 = 30 bags of cement required (1440/50) say 30 bags
Cement = 0.214 x 30 = 6.42 bags
Sand = 0.214 x 2 = 0.428 m3
Aggregate = 0.214 x 4 = 0.856 m3
| Is This Answer Correct ? | 8 Yes | 4 No |
how to control PQI (Project Quality Index)
4. What is your philosophy / attitude towards work?
Can anybody help by describing each and every step in short, used while giving a building layout by total station? Regards
how many bags of cement,sand and Aggregate to p.c.c. of 1:2:4 ratio.
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
How we can calculate cement and sand for a wall 25ft x 28ft.Thickness of wall is 9inches.
pls give me some basic informations in construction of a structure?
As per IS 2502 2(A+B)+24d formula is given for stirrups detailing,but explination not given for how that 24d came
mix design procedure for 1:6 cement mortar
how to calculate mivan shuttering matrial
can anybody provide me the HPCL apptitude papers?am having the test on march 2008 so plz
what is the specification for silt content in sand
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)