how to find out the quantity of cement sand and aggregate
in slab and flooring
at first volume i.e lenght ,breadth , hieght
den for eg.
a) For 1 m3 of concrete Mix 1:2:4 (M15)
Add 50% for wet concrete = 1.50 m3 or 1.52 m3 or1.55 m3
= 1.50/(1+2+4) = 0.214 m3
For 1 m3 = 30 bags of cement required (1440/50) say 30 bags
Cement = 0.214 x 30 = 6.42 bags
Sand = 0.214 x 2 = 0.428 m3
Aggregate = 0.214 x 4 = 0.856 m3
| Is This Answer Correct ? | 8 Yes | 4 No |
Is there the dry coefficient of cement is constant?
how to mack bbs
What's is mean by survey
TELL ME THE EQUATION FOR OGEE SPILLWAY
why elongation index is not required for concreteing coarse aggregate..
i have open space in my house, i want to make pcc there, si want to know how i calculate material , my area measurement is 10' x 10' x .25', pls tell me how much need cement, sand, concrete,if possible u than pls tell me the formula
What is difference between combin footing & rapt footing
what is the diff between sudden loading and impact loading?
How much quantity of steel will be used for commercial building consists of ground floor shops, first floor shops, second floor will be for offices and third floor will be office/banks. How many tons of steel is required to construct this building.
what is the logical concrete mix design for M 30 Grade and the cement consumption per M3
show answer/calculate mix 1:2:4 ratio -cement-sand -metal-water
How could I calculate quantities of fine aggrigates(sand) & coarse aggregates in pcc M15
1 Answers Coromandel, RECPDCL,
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)