how to find out the quantity of cement sand and aggregate
in slab and flooring
Answer Posted / hiten patel
at first volume i.e lenght ,breadth , hieght
den for eg.
a) For 1 m3 of concrete Mix 1:2:4 (M15)
Add 50% for wet concrete = 1.50 m3 or 1.52 m3 or1.55 m3
= 1.50/(1+2+4) = 0.214 m3
For 1 m3 = 30 bags of cement required (1440/50) say 30 bags
Cement = 0.214 x 30 = 6.42 bags
Sand = 0.214 x 2 = 0.428 m3
Aggregate = 0.214 x 4 = 0.856 m3
Is This Answer Correct ? | 8 Yes | 4 No |
Post New Answer View All Answers
what is shuttering co efficient?
how many men days of loburs and masons are requirete for 1 cum,pcc (1:2:4),Pcc(1:3:6) and Pcc(1:4:8) thanking you
Please let me know what is the simplest way of Calculating Mix Designs
why we are using stub column..? is it possible to construct steel stub column..?
What is demising walls?
how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?
I am called for interview from north east power plant .so, I need some interview question which may help me.
How to use of me trial wall plaster 6mm , 10mm par sqm. use in sand and cement ?
i want to ecil (Electronics Corporation of India Limited Hyderabad) previous civil engineering question papers immediately please.............
what is m30 in concrete tiles
how to do sudoko puzaals?
What is quantity of cement and sand required for 2000sqft of tiling?
what is the weight of 10mm,20mm,40mm aggregate
what is raft foundation
Define aligned dimension?