1.How much strength will be attained for M30 grade of
concrete after 28 days?
2.Is it attain 30 N/mm2 or target mean strength?
Answers were Sorted based on User's Feedback
Answer / bidyut dey
1.after 28 days it will be attained 30 N/MM2
2.Terget mean strength
| Is This Answer Correct ? | 29 Yes | 4 No |
Answer / ganaaji harsha
M30
Target strength for mix proportioning
f’ck = fck 1.65 s
Where
f’ck = Target average compressive strength at 28 days,
fck = Characteristic compressive strength at 28 days,
s= Standard deviation
From Table 1 standard deviation, s = 5 N/mm2
Therefore target strength = 30 1.65 x 5 = 38.25 N/mm2.
Target Mean Strength for M30 ( IS 456)
Fck 0.825*Standard Deviation
30 0.825*5
34.12
| Is This Answer Correct ? | 15 Yes | 1 No |
Answer / chandrasekhar j
1.30 n/mm2
2.it is target mean strength
| Is This Answer Correct ? | 11 Yes | 7 No |
Answer / shubham singh
1: M30
Target strength for mix proportioning
f’ck = fck + 1.65 s
Where
f’ck = Target average compressive strength at 28 days,
fck = Characteristic compressive strength at 28 days,
s= Standard deviation = 5 (IS 10262:2009, table 1)
From Table 1 ( IS 10262:2009, Clause 3.2)
f’ck = 30 + 1.65 * 5
= 38.25 N/mm2
2: It should attain target mean strength
| Is This Answer Correct ? | 3 Yes | 1 No |
Answer / aditya mayekar
1.after 28 days it will be attained 30 N/MM2
2.Terget mean strength
| Is This Answer Correct ? | 2 Yes | 3 No |
what is concrete canvas?
reinforcement slab, beam and column formulas?
what is meant by skyscapers?
importance of the soundness test to determine the quality of cement use for any construction
flow of fluid takes place viscosity compressibilityu surface tension deformation under shear force
I am doing a engineering contract with GOI. I have purchased certain material from outside Maharashtra and paid CST on that material @ 5.25%. Please intimate whether I will be liable for VAT or VAT on works contract or not.
structural engineering based
where tie beam is used? what is the pupose? what dimension of tie beam can provided and number and diameter of steel bars to be used between the columns of 1333mm and 1400.
the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm
what is thumb rule for calculating the size of ISMB required for a particular length of span
how much steel provide in 1m cube r.c.c
Which is the best book for building construction?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)