1.How much strength will be attained for M30 grade of
concrete after 28 days?
2.Is it attain 30 N/mm2 or target mean strength?
Answer Posted / shubham singh
1: M30
Target strength for mix proportioning
f’ck = fck + 1.65 s
Where
f’ck = Target average compressive strength at 28 days,
fck = Characteristic compressive strength at 28 days,
s= Standard deviation = 5 (IS 10262:2009, table 1)
From Table 1 ( IS 10262:2009, Clause 3.2)
f’ck = 30 + 1.65 * 5
= 38.25 N/mm2
2: It should attain target mean strength
| Is This Answer Correct ? | 3 Yes | 1 No |
Post New Answer View All Answers
For the calculation of bearing pressure below the footing, to know whether it is below the safe bearing pressure of the soil, the unit of RCC below ground level to be taken is 25 KN/m3 or (25-15)KN/m3, where 25 is the unit weight of RCC and 15 is the unit weight of soil and whether the weight of backfilling to be taken?
how i get all type of short type question answer about civil engg
List out the potential risk factors for workers on the construction site?
Advantage of Aluminum form work in terms of activities can be skip and cost too
GIVE US YOUR FULL DETAIL OF THE FOLLOWING… FULL NAME.. PERMENENT MAILING ADDRESS DIRECT CONTACT NO E MAIL ADDRES.
What are the joints wants to made in masonry where door opening, arches like etc..
What is rate for brick masonry work of 1.0 m3 in cm 1:6?
There are two buildings one taller and one shorter whose time period will be grater and similarly the frequency ?
which steel is better for residential building tmt steel or hysd steel
Define What is the force exerted by the Tacoma narrows bridge?
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
What is the substitute of Mastic Asphalt?
In a beam,stirrups are placed closely at ends than at centre due to shear.similarly where would ties be closer to each other-at center or at ends in a column and slab.
How can calculate the requirement of steel bars of rcc slab for 1100 sq ft?
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?