1.How much strength will be attained for M30 grade of
concrete after 28 days?
2.Is it attain 30 N/mm2 or target mean strength?
Answer Posted / bidyut dey
1.after 28 days it will be attained 30 N/MM2
2.Terget mean strength
| Is This Answer Correct ? | 29 Yes | 4 No |
Post New Answer View All Answers
why development length = 50D . why not 100D
how to caliculate required amount of cement and sand required for 1cu.m.
What things architect have to take care of before starting any project?
What does civil engineering mean?
what are the five benefits of using standard terminology in the measurement process?
Dear Sir, I work in hydro project. I want to hire Scorpio/ Bolero on monthly basis. But how can i justified its amount (Hourly basic). Please solve my problem
how to remove the quantity of metal 1 and metal 2 in concrete
WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT
Define mirror?
what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?
What is the effect of a building collapse?
How to come 1.54 from dry to wet concrete?
how do you calculate the quantity of steel,cement for plinth beam. (example size 41'*0.58'*1.08')
whats is difference between anchorage length and development length
What was asked in isro civil interview