Can anybody tell me how to calculate the quantity of a
trapezoidal footing?With its formula and an example.
Answers were Sorted based on User's Feedback
Answer / raju
Right formula is = V = [L X B X d] + h / 3 [ A1 + A2 + ROUTE
UNDER A1 A2 ] where , l = length , b = breadth , d = bottom
depth , h = D - d , A1 = bottom area , A2= top area (ii) is
= V = [L X B X d] + h/6(A1 + A2 + 4 Am) where , h = D - d ,
A1 = bottom area , A2= top area, Am = Mean of Top and Bottom
Area
feel free to call me
Raju
Engineer-Civil
9999213613
DLF
| Is This Answer Correct ? | 60 Yes | 3 No |
Answer / raja j
in trapezoidal footing we seperate the footing as two
parts.one is rectangle another is trapezoidal
for taking rectangular portion= (L*B*d)
L=length of footing
B=breath of footing
d=footing depth (at the end of rectangle portion height)
for taking trapezoidal
v=h/3((A1+A2)+sqrt(A1A2))
V=volume
A1= footing area (L*B)
A2= column area+ add 50mm for each side ((l+100)+(b+100))
h=height difference(D-d)
finally,
Add =rectangle+trapezoidal
= (L*B*d)+h/3((A1+A2)+sqrt(A1A2))
Raja.j
9626389621
| Is This Answer Correct ? | 9 Yes | 5 No |
Answer / jigar soni
V = [L X B X d] + h/6(A1 + A2 + 4 Am) where , h = D - d , A1
= bottom area , A2= top area, Am = Mean of Top and Bottom Area
| Is This Answer Correct ? | 5 Yes | 1 No |
Answer / s.prabhu
Please divide the footing in to 2 parts i,e 1) Bottom
rectangular portion & 2)top slope portion
Total volume (V) = v1+v2
Volume of bottom / rectangular portion is called as Volume
(v1)
Volume of top / slope portion is called as Volume (v2)
V1 = L1xB1xh1
V2= h2/3* (a1+a2)* square root of (a1+a2)
L1= length of bottom portion
B1= breadth of bottom portion
h1 = height of bottom portion
L2 = length of top portion
B2= breadth of top portion
h2 = height of top portion
a1= area of bottom bottom Portion = L1*B1
a2 = area of top rectangle portion= L2 *b2
For any clarification
Please call
S.Prabhu
9901702081
| Is This Answer Correct ? | 7 Yes | 4 No |
Answer / krishna kumar.a
Quantity = 1/6*(top area+bottom area+ 4* mean area)
Example
top length =3m, width =2m
bottom length =5m , width =4m
height =1m
Top area =3*2 = 6 sqm
Bottom area = 5*4 = 20 sqm
Mean area =(5+3)/2*(4+2)/2 = 12 sqm
Quantity = 1/6*(6 + 20 +4*12)= 12.33 cum
| Is This Answer Correct ? | 9 Yes | 7 No |
Answer / sekar.k
QUANTITY CALCULATION FOR TRAPEZOIDAL: 1/2*H(A+B)*L
EXAMPLE:FOOTING TOP WIDTH:2.00M
FOOTING BOTTOM WIDTH:4.00M
FOOTING HEIGHT :6.00M
FOOTING LENGTH :10.00M THEN,
QUANTITY OF TRPEZOIDAL FOOTING :
1/2*H(A+B)*L
1/2*6.00(2.00+4.00)*10.00
1/2*6.00(6.00)*10.00=180.00CUM
| Is This Answer Correct ? | 5 Yes | 4 No |
Answer / nadim
divide into 3 parts 1st into 2 traingles and 1 into a rectangle we all know the area formula then multiply the area with the remaining dimension
| Is This Answer Correct ? | 1 Yes | 12 No |
what are the compressive strength requirements(in 7 days & 28 days) of cement sand mix used for plastering purpose (Cement:sand-1:6)? Kindly give the IS Code reference also.
If drainage is main things then which respect the super Elevation may be provided?
How to calculate the no of bags required for 12mm thick 1:6 plastering?
infosys campus ques... u drive a car,nmb of d car is KA17M8719. it leaves at10:26am frm davanager to bangalor which is264km away at a speed of 95km/hrCar reachs bangalor at 4:18pm. nw tel me wat is d date of birth of drvr
9 Answers Ernst Young, Infosys,
material required for construction of 1cu.mtr wall (Cement, No of bricks (Brick size 40cm x 20cm x 10cm),sand,Quantity of water
How can we compact the soil on slope portion? What is the Grade II of Stone Metal?What type tests carried out on BBM road?
how to prepare the bar bending schedule for a given rcc material?It will be more helpful if you explain me with an example?
Define a polyline?
Would you cause a 55-gallon drum of water to weigh more by climbing in?
What is demising walls?
Do you expect there to be many jobs for civil engineers going into the future? What are the three main drawbacks of being a civil engineer? What are the three best things about being a Civil engineer? What amount of vacation time is available to you? Is the time paid? What are the usual hours of work required? Is it possible, or common, to work from home? How much time do you spend on the site of your projects? What type of schooling is required to be a civil engineer? How many years are required to complete this education?
howto calculate the quantities of material used in fly ash brick after finding the volume??
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)