what is slump

Answers were Sorted based on User's Feedback



what is slump..

Answer / mirza9724

the test for checking workability of concrete.

Is This Answer Correct ?    32 Yes 1 No

what is slump..

Answer / ashish dubey

Slump is an arbitrary measure of workability.fresh concrete
filled in slump cone subsides when cone is taken up.this
subsidence of concrete measured and recorded as
slump.however same slump can be obtained for different
workability of concrete.day to day check on site.too high
and too low slump gives immediate warning.

Is This Answer Correct ?    9 Yes 0 No

what is slump..

Answer / madhucsm

slump is defined as the concrete fall in top that much

Is This Answer Correct ?    9 Yes 2 No

what is slump..

Answer / mani.g

preparation concrete mini 75mm
Reamix Conc minimum slump 100mm

Is This Answer Correct ?    0 Yes 1 No

what is slump..

Answer / sagar boda

slump test gives constitency of cememt ,not give workability.

Is This Answer Correct ?    2 Yes 6 No

Post New Answer

More Civil Engineering Interview Questions

How to increase a bearing capacity of soil?

0 Answers  


What are wooden shingles?

0 Answers  


How to calculate the weight of sand am 20mm course aggregate in 1 c.m M25 concrete Which use 400 kg of cement ?

0 Answers  


what do u mean by shear?and tension?

6 Answers   L&T, Shoba Devlopers,


What ingredients with% found in ppc cement??

0 Answers  






undisturb samples are obtained by direct excavation thin walled sampler thick walled sampler none of this

1 Answers  


how much quantity of work we can get by rod benders per day

3 Answers   IVRCL, NCC, OWDM,


How t find the quantity of materials required for construction of a wall of length 10x5x0.2

2 Answers   NCC,


how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.

0 Answers   CPWD, HGS,


at the beam-column junction point tell me how much beam bars should pass through column ring ? 3 or 2 or 1 . answer with reason. if it is not happen then what will be he effect ?

1 Answers  


How much used for sand per square meter in 12mm Thickness

1 Answers  


Define slump in terms of slump test

6 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)