if a pipe those configuration (ASTM c 76 class b 450mm dia
2500mm length) fixing for water course those lining of water
is 7000 running meter.
my question is that if 8 joints of pipe ls leakage and we
have not permission to stop the water so which treatment we
apply on joint in that in condition.



if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course ..

Answer / Sukhwinder Singh

In the given scenario, since it's not possible to stop the water flow, a temporary solution would be needed to control the leakage. Applying a waterproof sealant or epoxy could help in sealing the leaking joints temporarily. However, this is only a short-term fix and permanent repair should be carried out as soon as possible when the water supply can be stopped. Regular monitoring of the pipe condition is also necessary to detect any further issues.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

What is the formula for figuring out how many gallons of water are in a pipe by the foot?

1 Answers  


how can i test sand on field in lebortry?.

4 Answers   ECCI,


What is bmc stands for in bmc software?

1 Answers  


why reinforcement is not provided at centre for beams r column

9 Answers  


What is the roll of face bars in beams

1 Answers  


What is the diff. Between rectangle & parallelogram?

10 Answers  


state the main objectives of underpinning

4 Answers  


what is the use of bottom reinforcement in Cantilever Beam?

4 Answers   McNally,


what is the difference between GSB & WBM ?

1 Answers   CBC,


A doubly reinforced concrete beam is 25 cm wide and 50cm deep to the centre of tension reinforcement. The centre of compression is steel is 5cm from the compression edge. The areas of the compression and the tension steel are 10.16cm2 and 12.56 cm2 if m=18 and the bending moment at the section is 7,000,000 N-cm. Calculate the stress in concrete and steel.

1 Answers  


what values & beliefs have guided you in your career path

1 Answers   IVRCL,


15mm thick plastering 1:4 what is the cement consumption per sqm

6 Answers   Well Care,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4453)
  • Electrical Engineering Interview Questions Electrical Engineering (16638)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)