cement constant for brick works
Answers were Sorted based on User's Feedback
Answer / senthilkumar
if we consider 1:6 ration for cement morter , the cemnt
weight will be 240 kg per m cube morter, normaly 10% volume
of morter will be consume for brickwork of volume. if 25%
means 0.250 m cube morter need for 1 m cube brick work, so
cement need for
calculation;
1:6
1/6*1440kg=240kg
if morter require=.25 m cube
=.25*240=60 kg cement required
| Is This Answer Correct ? | 9 Yes | 6 No |
Answer / gopal
cement constants can be calculated if we know the ratio
cement and sand.
| Is This Answer Correct ? | 1 Yes | 1 No |
what is difference between NP2 NP3 NP4 CONCRETE HUME PIPES USED AT SITE
Consumption of Binding wire for fixing of cover block in vertical surface
How we calculate the service time of buildings
how can change 10mm dia @130c/c bar spacing to 8mm dia
How much depth of excavation have to do for Highrised builldings?if Raft foundation how much,and Pile foundation how much?
How much time Required for PPR pipe network testing
what isload waring calculation
How many litres of water used for curing of 1000sqft of slav
2nd and 4rt angle elevation used in which country ?
what"s the purpose of dry lean concrete(DLC)and where it"ll be use it?
How to calculate laplength for 3 floors
how much is the maximum compressive strength of soil cement and soil-cement-microsilica .
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)