Trapezoidal section footing calculation of Volume & its Area
Answer Posted / chandramouli bv
V=(L X B X d) + h/3(A1 + A2 + SQRT(A1 X A2 )
L=Length of footing
B=Breadth of footing
d=Depth of bottom portion
h=Height of trapizodial portion (D-d)
A1= Area of bottom portion (L X B)
A2= Area of top portion (l X b )
| Is This Answer Correct ? | 37 Yes | 5 No |
Post New Answer View All Answers
a butt weld is specified by
01. a. Diagram of a slump cone…………… 1 b. Size of Slump Cone…………… 1 c. Volume of a slump cone by av. Dia method…………… 1 d. Volume of a slump cone by av. area method…………… 1 e. Volume of a slump cone by frustrum method …………… 1 f. Angles of slump cone …………… 1 g. Slump measured by slump cone due to…………… 1 h. Slump does not measured by cylinder / cube due to …………… 1 i) ii) i. Slump cone is to be filled in……………………..Layers.
Which prize is the alternative to the NOVEL Prize?
how to balance aggregate during mix design of concrete???? how to calculate moisture content like C/A,F/A and how many percentage using ice instead of water for example of we are preparing ice concrete??????
how to calclate the SHUTTERING TAKEN CONCRETE LOAD? WHAT IS THE LOAD BEARING CAPACITY IN STEEL SHUTTERING PLATE? WHAT IS THE CONCRETE LOAD IN (MASS) IN THE SHUTTERING PLATE. PLATE SIZE IS 120CM* 90CM CONCRETE WALL LENGTH IS 10M ,WIDE IS 60CM, HEIGHT IS 1.2M PLS TO SENT THE CALCULATION.
Explain the different types of building contracts?
what is the difference between np2 and np3 concrete mix
How is improve my knowledge in construction industries....
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer
Rate analysis of Vitrified tile in cement mortor 1:3
what r the precaution for high in atp tempareture,low in atp tempareture
How to identify the vitrified tile and ceramic tile by observation only after executing the job.
Design a cantilever type retaining wall to retain sand for 4m above the ground. The sand fall slopes at the rate of 1 vertical to 2 horizontal. The weight of sand is 18000 N/m3, the angle of repose being 30. The safe bearing capacity of the soil is 200 kn/m2 at 1/25m below the ground level. Use m 15 concrete mix.
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting?