Answer Posted / v.kannan
while joining of new roof slab to existing one you should
ensure whether existing roof having reinforcement projection
for joining or not to new reinforcement. if not you want to
remove the concrete up to 150-300 mm from the edge and clean
the surfaces and existing bar then connect the new one and
we can make the concrete through proper form work. and the
grade of the concrete should not less than M25
| Is This Answer Correct ? | 29 Yes | 7 No |
Post New Answer View All Answers
Can we use concrete of slump cone in cube casting in which we have already measured slump?
strength of bitumen concrete with 80-100 & 60-70 grade bitumen
What is aggregate?
How will drive weight formula for circular cylinder steel bar in kg/ m please step by step drive?
Wat is meant by Aecron brick?
What is capicity of cap lock scffolding stander(vertical member) and ledger of different size?
what is called the inverd level of mabhole chamber?
writte a c prog. to acept 5 no. from consule and then display them back on consulte in ascending order
Describe about the Pile test methods, which are used in Industrial & Multistory Buildings in general.
beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?
Which prize is the alternative to the NOVEL Prize?
the magnitude of the buoyant force can be determine by newtons law of viscosity archimidies principal principles of momemnt none
what are the ffactors you considered choosing the course?
The concrete slump recommended for beams and slabs; is?
Scaffolding IS code NO.