Answer Posted / v.kannan
while joining of new roof slab to existing one you should
ensure whether existing roof having reinforcement projection
for joining or not to new reinforcement. if not you want to
remove the concrete up to 150-300 mm from the edge and clean
the surfaces and existing bar then connect the new one and
we can make the concrete through proper form work. and the
grade of the concrete should not less than M25
| Is This Answer Correct ? | 29 Yes | 7 No |
Post New Answer View All Answers
I need to do a Compressive Strength Test for a specimen made of Rubber. Before doing the Test on the Machine, I need to have an idea of the Minimum and Maximum Compressive Strength or Yield Strength of the specimen. How can I calculate that?
Technical Question of Civil Engineering
how to determine H- zone in a column? where it will occur?
why +1 to be followed for calculating the no of bars in BBS. Please explain
The largest size of paper used in plotter to print the drawing made by Autocad .
if i used salt as a add mixture in concrete, then what will happen and what are the naturally available add mixtures.
What does civil status mean?
How many types of slabs are there & how to design it?
How to calculate paint drums per meter square
Iwant to calculate the production of 1 labour for concrete casting which includes shuttering,scaffolding,steel fixing,concreting, deshuttering and curing in 8hours.But i am not able to determine it approximately would you pls.??
Formula of mid span bar
how can i calculate cement in brickwork
Formula of area of crane hook
What is the difference between linear dimension and aligned dimension?
how to calculate the chair reinforcement length in slabs, footing or anywhere??