How to calculate Cement, Sand and Kapachi required for M20,
M25
Answer Posted / kanchan
M20=1:1.5:3,
1cum concrete with water= 1.57cum dry material
For Cement- 1/(1+1.5+3)*1.57=0.285cum=8.55bags
For Sand- 1.5/(1+1.5+3)*1.57=0.43cum
For Aggregate -3/(1+1.5+3)*1.57=0.86cum
M25 -1:1:2
For Cement- 1/(1+1+2)*1.57=0.39cum=11.77bags
For Sand- 1/(1+1+2)*1.57=0.39cum
For Aggregate -2/(1+1+2)*1.57=0.78cum
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
cause of cylinder test failure
What is the minimum size of the particles of silt soil?
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
what is the mix design for M:60 with micro silica andmetakaoline?
why do we not deduct volume of steel to find actual volume of concrete in practical???
What is the origin of name railway sleepers?
how much used soil in 1 brick of standard size?
Technical Question of Civil Engineering
what is the calculation of raw material for 0.35cum of m-15
What is the software used in civil engineering?
What is the meaning of soil reinforcement?
at which depth the construction of tunnel is economical from cost and engineering aspect.
What is the difference between built area and super built up area?
I am in India. Employer A got approval for my H1. But they have no job for me now. Company B is going to file H1 for me. They do not know about company A. Is there any way that I get approved H1 of company A transferred to Company B?
How to test cement,sand,20mmbluemetal,40mmbluemetal,bricks,concrete by visual and instrument