How to calculate Cement, Sand and Kapachi required for M20,
M25
Answer Posted / kanchan
M20=1:1.5:3,
1cum concrete with water= 1.57cum dry material
For Cement- 1/(1+1.5+3)*1.57=0.285cum=8.55bags
For Sand- 1.5/(1+1.5+3)*1.57=0.43cum
For Aggregate -3/(1+1.5+3)*1.57=0.86cum
M25 -1:1:2
For Cement- 1/(1+1+2)*1.57=0.39cum=11.77bags
For Sand- 1/(1+1+2)*1.57=0.39cum
For Aggregate -2/(1+1+2)*1.57=0.78cum
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What is meant by cartesian coordinate system?
In a concrete grade C35A, C & A stands for what and equalent cube strength?
how to remove the quantity of metal 1 and metal 2 in concrete
What is the release of lien?
Define What is unit weight of normal concrete?
Why Vitrified tile are getting pop up.
design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal
plz.show development and anchorage length in simple diagram.
What is factor not to be taken in consideration in mix design?
how clculate excavated or backfilling quantity by simpson's rule
What are the common ways of demolition?
Dear Frds, How can i calculate the Steel for RCC Slab, Please provide one Example also, so that i can understand very well. Ex: Area: 1320.0 Sft.(44' X 30') Span: 15'(Default). Column Size: 9"X15"(6 No.s 12mm Rods) Please Provide Calculation Details. Thankyou. Satish
from one meter cube of stone masonry structure how much cubic meter of cement mortar we use as our estimation 25-30% is that correct for estimation of quantity of sand and cement(2:1) proportion of mortar
how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.
how much used soil in 1 brick of standard size?