E.B sending end to receiving end 33kv ug cable laid
8Km,receiving end to ss1,ss2,ss3,ss4 all are Approx 800
Mtr,can go for 33KV to 430V or 33kv to 11kv in receiving end
and 11kv to 430 near ss ,which one is good for technically
and economically.
Answer / tapas
Receiving end----- should be 33/11 KV
l
l Distance between Receiving ss and distribution is 800 Mtr
l
ss-1, ss-2, ss-3, ss-4-- -- Should be 11000/430 V
This option is better as 800 Meter cable cost for each substation will be lower in HT and loss will be lower
| Is This Answer Correct ? | 2 Yes | 0 No |
what is mathed of check the D.C MOTOR 181 KW (ARMATURE AND FIELD) WHAT IS THE MATHED OF CHECK THE THYRISTOR MODULE (HIGH CURRENT)
difference between load bus and dead bus?
What motor is used in ceiling fans and what motor is used in table fan.? why table fan is costlier than ceiling fan?
why cannot we use a freuency more than 400hz is used in aircrafts?
what is meant by form factor and hoe related with the HT transmission voltage
why induction generators are used in wind mills.why cant synchronous generators b used??
WHAT DO U MEAN BY THERMAL OVER LOAD RELAY& WHERE THEY ARE BUSED
Why earthing is required, and what effect in earthing result is more than 5 ohm and less than 5 or equal to 0 ohm
Single line digram for 11 kV to distribution use go,la and do
what is the potential difference between line and earth?
which inert gas is most apt to be used in a fluorescent lamp?? why ??
What are insulation classes? Tell examples of each of them.
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)