E.B sending end to receiving end 33kv ug cable laid
8Km,receiving end to ss1,ss2,ss3,ss4 all are Approx 800
Mtr,can go for 33KV to 430V or 33kv to 11kv in receiving end
and 11kv to 430 near ss ,which one is good for technically
and economically.
Answer / tapas
Receiving end----- should be 33/11 KV
l
l Distance between Receiving ss and distribution is 800 Mtr
l
ss-1, ss-2, ss-3, ss-4-- -- Should be 11000/430 V
This option is better as 800 Meter cable cost for each substation will be lower in HT and loss will be lower
| Is This Answer Correct ? | 2 Yes | 0 No |
What is the difference between earthed and unearthed power cable.
what is the use of neutral displacement relay
how current is reverse from its normal direction during the fault?
how point on wave controller works.
If SFU is Switch Fuse Unit, What is the expansion for FSHF in Electrical Engineering?
what happens when current(ac or dc)flowing through a boucket of water?please describe it.
what happens if a carbon brush is touching the top end of the commutator
What is UPS?
Why only plate(copper) Earth pit given for neutral earthing? why not pipe(G.I) Earth pit?
practicalLY what is impedence ...?
How seriving & testing of the HT & LT breakers are done. What are the standard Ir values on which we can come to know the test is passed or failed?
what is the use of interposed & reverse voltage transformer
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)