E.B sending end to receiving end 33kv ug cable laid
8Km,receiving end to ss1,ss2,ss3,ss4 all are Approx 800
Mtr,can go for 33KV to 430V or 33kv to 11kv in receiving end
and 11kv to 430 near ss ,which one is good for technically
and economically.
Answer Posted / tapas
Receiving end----- should be 33/11 KV
l
l Distance between Receiving ss and distribution is 800 Mtr
l
ss-1, ss-2, ss-3, ss-4-- -- Should be 11000/430 V
This option is better as 800 Meter cable cost for each substation will be lower in HT and loss will be lower
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is meant by earthhing of a magnetic flow meter and when to use empty pipe detection?
How will A Medium voltage circuit breaker(11 kV voltage level) operate under short circuit fault condition whether It is having short circuit release like Low voltage circuit breaker or relay should be given?
Draw torque - speed curve and load curve of induction motor? mark operating point ?
Define transfer function?
What is industrial plc
what will be d.g. capacity to cater together for 14hp A.C. load & 3kw lighting load
how does ELR works? explain
On what basis the the size of Lightning arrester for buildings are selected ?
10 tube light connect in mcb breaker.one tube light is fault.so breaker is tribe.how fault is rectified.(using 3wire phase,earth,neutral)
can indirect loading be called as phantom loading?
how to calculate maximum current
What is lifting power for 1 wb/m2 and 1 A magnet?
What is the emf equation of a transformer?
What would be the size of wire used for 2 Ton of window A.C?
Is there any guideline say about display of earthing value near to earth pit