Answer / praman kumar srivastava
Providing, erecting, fixing in position striking/ removing
and cleaning shuttering and centering for formwork in
foundation and Plinth at all locations for all shapes
inclufing chamfers, camber, splays, keys, wedges, props,
rail, bracing , brackets, cutti
Foundation. For 10.8 Sqmt Area (Based on Physical Analysis)
Material :
Ply Wood Sqmt 11.000 538.000 5918.000
Nut Bolts, Balli Battens etc LS
1095.000
For 15 Repetation 7013.000
For 1 467.533
Labour :
Carpenter I Class Nos 0.750 175.000 131.250
Beldar skilled Nos 1.500 135.000 202.500
Shuttering Oil LS 1.000 33.400 33.400
Sundries I Time 16.700 1.690 28.223
862.906
Add for water charges @ 1%
8.629
Total 871.535
Add for contractor's profit and overheads @ 10%
148.161
Cost for 10.8 sqm 1019.696
Cost of 01 Sqmt 94.416
Say 94
Is This Answer Correct ? | 7 Yes | 2 No |
strenth of brick
What is water/cement ratio? Importance in construction?
what is the water-cement ratio of mix design while 30mpa in 7 days?
if we get water mor from 28 days to the rcc concret is this better or have a damag
Types of pile, which should be prefer in sandy soil
For 12mm thick and cement plastering 1:6 on 100sqm new Brick work the quantity of cement required is
How to find out slope footing concrete
0 Answers Ekta World, Punj Lloyd Ltd,
how to cement bag calculate m25 grade
cement mortar 1:6 explain the cement and sand coefficient calculation?
what is moment-curvature relationship in semi rigid connections??
how much need cement bags for block work of wall approx 1000 hollow blocks 20x20x40cm
How to calculate the quantity of cement in Cement Mortar M10 Concrete using 40mm metal