Any bopdy tell me how to prepare rate analysis for
Centering and shuttering for RAFT FOUNDATION, SUSPENDED
FLOORS, STAIR CASES, RETAINING WALLS, SHEAR WALL and COLUMNS
Answer Posted / praman kumar srivastava
Providing, erecting, fixing in position striking/ removing
and cleaning shuttering and centering for formwork in
foundation and Plinth at all locations for all shapes
inclufing chamfers, camber, splays, keys, wedges, props,
rail, bracing , brackets, cutti
Foundation. For 10.8 Sqmt Area (Based on Physical Analysis)
Material :
Ply Wood Sqmt 11.000 538.000 5918.000
Nut Bolts, Balli Battens etc LS
1095.000
For 15 Repetation 7013.000
For 1 467.533
Labour :
Carpenter I Class Nos 0.750 175.000 131.250
Beldar skilled Nos 1.500 135.000 202.500
Shuttering Oil LS 1.000 33.400 33.400
Sundries I Time 16.700 1.690 28.223
862.906
Add for water charges @ 1%
8.629
Total 871.535
Add for contractor's profit and overheads @ 10%
148.161
Cost for 10.8 sqm 1019.696
Cost of 01 Sqmt 94.416
Say 94
| Is This Answer Correct ? | 7 Yes | 2 No |
Post New Answer View All Answers
where tie beam is used? what is the pupose? what dimension of tie beam can provided and number and diameter of steel bars to be used between the columns of 1333mm and 1400.
how much repeitation for conventional and maivan formwork?
How to calculate density of 40 mm coarse aggregate, in mixing ration 1:1.5:3? Please explain calculation for density
What are segregation and bleeding?
What is unit weight of normal concrete?
if dia of slab beam bar is38mm what its clear cover any method of provide clear cover
What is the maximum strength of cub compress strength in one cub testing
why is the column design?
Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.
for 200 kg of cement how is the mix proportion in kg for m25 grade of concrete
how to conversation of all construction material in to brass
What are the advantages and disadvantages of lead products in construction?
how do you calaculate the total steel quantity of an rcc building using thumb rule?
Why are separation membranes used between concrete pavement slab and sub-base?
What are the methods of measurement? Describe it shortly