Any bopdy tell me how to prepare rate analysis for
Centering and shuttering for RAFT FOUNDATION, SUSPENDED
FLOORS, STAIR CASES, RETAINING WALLS, SHEAR WALL and COLUMNS
Answer Posted / praman kumar srivastava
Providing, erecting, fixing in position striking/ removing
and cleaning shuttering and centering for formwork in
foundation and Plinth at all locations for all shapes
inclufing chamfers, camber, splays, keys, wedges, props,
rail, bracing , brackets, cutti
Foundation. For 10.8 Sqmt Area (Based on Physical Analysis)
Material :
Ply Wood Sqmt 11.000 538.000 5918.000
Nut Bolts, Balli Battens etc LS
1095.000
For 15 Repetation 7013.000
For 1 467.533
Labour :
Carpenter I Class Nos 0.750 175.000 131.250
Beldar skilled Nos 1.500 135.000 202.500
Shuttering Oil LS 1.000 33.400 33.400
Sundries I Time 16.700 1.690 28.223
862.906
Add for water charges @ 1%
8.629
Total 871.535
Add for contractor's profit and overheads @ 10%
148.161
Cost for 10.8 sqm 1019.696
Cost of 01 Sqmt 94.416
Say 94
| Is This Answer Correct ? | 7 Yes | 2 No |
Post New Answer View All Answers
Questions related to civil.engg in company
What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?
Define a polyline?
How to plan a project
How to calculate the quantity of ingredients of M20 grade concrete?
pls mail some more tecnical qustions at msaranya2610@gmail.com
To pcc 11 ft x 24 ft .How many bags of cement, sand and aggregate required? And for roofing how many cgi sheets required?
What is Time period of a building and its relation with frequency ?
How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57
HOE TO YOU PLAN TO ACCHIEVE THE GOALS?
When column of building is abutting the boundary line,then suitable footing advised is
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
Basic questions of civil engineering
The building has 12 columns of 12x9 in 3 rows of 4 each in a plot of 50'x30', The central row is strengthened with 16mm twisted rods. The roof area is 1500 sft including balconies. calculate the load factor per sft. Also indicate the number of roofs the building can withstand.
When was the first motorway built in england?