how to check the stabilty test for generator differential
protection
Answer / raghavendran
Checking of the pickup and dropout value
When checking the pickup value, the analogue input signals
of the single phase alternating test current have to be fed
to the relay via terminals.When testing the pickup value,
the alternating test current must first be lower than the
set pickup value.
Then the current will be increased until the relay picks up.
The value that can be read from the ammeter may not deviate
by more than ± 2.5% of the setting value. The tripping
values for the other current inputs should be checked
accordingly.
Function test
Disconnect all leads for adjusting the interposing C.T.s and
perform the following function test:
Load the generator with minimum 50% load. Assure that the
tripping of the generator C.B. does not cause un-wanted
damages (blackout).
To operate the differential relay use a shorting link
between one of the phase measuring sockets
and GND, e.g. connect Line to GND. The relay should trip
immediately. If no trip occurs, make sure
that the load current exceeds the set value.
| Is This Answer Correct ? | 0 Yes | 1 No |
draw single line diagram of UPS
1 Answers Adani Ports, Equate, IBM, SAP Labs, Socomec, TATA,
In a large office how do we calculate required number of light fittings, assuming fittings are 4x18W or 2x36W fluorescent fitting ?
What is the difference in Line PT & Bus PT.
why current flow throgh conductor.
Can we generate 3 phase power from single phase connections?? If yes, how?
what is feed back and what are feed back amplifiers?
What is auto changeover and how it works plz write details.
What is the fullform of NS fuse
2 Answers Google, JAL International,
We are dealer in Maharashtra State & We have recd. form C from dealer of Maharashtra State against our E-1 form. Now assessing authority is asking for counterfoil of our E-1 form. But, our E-1 form counterfoil is misplaced somewhere & assessing authority is disallowing the C form which is recd. from Maharashtra State.Please let us know the option for allowing C form?
for opening electrical shop, tips needed.
WHAT ARE THE DATAS REQUIRED FOR SCS SIGNAL LIST PREPARATION?
What is control system?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)