why loss of strength in concrete in 7 days cube test i am
not geting mim 7 days strength that is 67 percent for M-35
and my mix design is perfect there is no doughty,and my
results are near to 7days percentage but not 67 percent.
Answers were Sorted based on User's Feedback
Answer / sjtbehera
what you sure about your mixing. you check slump test, you
check bulkage of sand, you check waste of cement while
mixing, you check compaction factor, if this is right then
result is not obtained please contact Indian standard Buero.
Is This Answer Correct ? | 12 Yes | 1 No |
Answer / bhauso mane
there are many reasons of concrete failure result as bellow
1)water to cement ratio - increasing water cement ratio
decreases the strength of concrete.
2)quality of cement- firstely check the quality of cement .
3)raw material properties like silt in sand,flaky,
elogation,& hardness of aggregate.
4)mixing & sampling of concrete.
5)compaction & curing of cubes.
6)test machine accuracy.
Is This Answer Correct ? | 9 Yes | 0 No |
Answer / v.purushotham
The fallowing check points to be done:
 In between interval you should check the mix ratio
i.e. volume/ weight of material,
 Check cement ratio,
 Check slump while pouring the concrete,
 Check the proper mixing of concrete,
 Check the procedure of filling and compacting of
cube mould,
 Check the bulkage of sand,
 Check the gradation of material every 15/ 30 days
interval and compare the designed materials properties,
 Last but not least check the proper curing of
concrete cubes.
Is This Answer Correct ? | 6 Yes | 0 No |
Answer / saeng
concret will get its 100% characteristic strength after 1
year only.
Is This Answer Correct ? | 2 Yes | 8 No |
what does the track parameter mean in staad.pro?
What is change order request?
what is minimum dimension for the kitchen & bed room
what is the max spacing of 2 columns upto which there is no need to put beam betwn dem.and how to fix the location of columns and beams in home construction.
how to calculate the wind pressure
How much for the BRC lapping in full yield and half yield < and which table to get it ?
we do not provide reinforcement bar through the centre of a column.why?
what is the stripping time of beam column & slab?
Please tell me about surveying standard chain details.Thanks.
please describe clear cover in column from stirups to face
Explain about Sulphate Resisting Cement ?
For G+4 storied building having 76000 sft per each floor, can you prepare schedule in such a way that structure should be completed with in 41/2 months and finishing be completed with in 51/2 months?